== KAGRA Commissioning status at DET meeting == * Date : 2022/07/04 === Overall schedule === * (In case of no trouble) * 6/20 - 7/1 Suspension commissioning Type-Bp (Continued) * 7/4 - 7/8 Interferometer commissioning (Alignment, Optics characterization, SRM replacement, ...) * 7/11 - 7/22 Suspension commissioning Type-B * 7/25 - 7/29 Acceptance check ~PR2 * 8/1 - 8/5 Closing the center area ~PR2 * 8/8 - 8/19 (Including Obon) Acceptance check ~SRM * 8/22 - 8/26 Closing the center area ~SRM * 8/29 - 9/2 Leak test * Mid size baffle installation (SR3, SRM) * SRM replacement (Week of 7/4) * ISS installation (Review 7/19) * High power laser installation (Week of 7/4) === Progress of commissioning === * X arm commissioning * End X IM 80K * Investigation of the noise in the new oplev light source * Y arm commissioning * End Y : Pumping down ongoing * Center area commissioning * Suspension health check Type-Bp's (Monitor, actuator, cabling) * PR2 and PR3 length sensing oplev seems strange, need to check * Mirror cleaning SR3 and SRM : Done * Investigation of the X-arm fiber noise cancellation * Precise alignment better, but not stable * We found the weak point around PR3, Miyoki-san fixed it and became better * New PDs are discussed * Study for installation of the new laser * Set inside the PSL room this week === Interesting data === * X arm cavity * Both IR and GR * Glitch investigation of the ITMX ADC * Glitch investigation of the MN oplev light source * Y arm commissioning * Both IR and GR * Center area commissioning * Main IR * ALS * IMC (Input Mode Cleaner) * ASC (Alignment Sensing and Control) done * Long term stability check * Beam power, beam position, oplev monitoring * Glitch investigation * Temperature dependence * Relationship between PSL room * With PEM channels * (Hammering test?) * OMC * Invesigation will continue after closing the center area * Because the BS is too fluctuate, it became difficult to investigate