== KAGRA Commissioning status at DET meeting == * Date : 2022/07/11 === Overall schedule === * (In case of no trouble) * 7/11 - 7/22 Suspension commissioning Type-B and PR2 * 7/25 - 7/29 Acceptance check ~PR2 * 8/1 - 8/5 Closing the center area ~PR2 * 8/8 - 8/19 (Including Obon) Acceptance check ~SRM * 8/22 - 8/26 Closing the center area ~SRM * 8/29 - 9/2 Leak test * Mid size baffle installation (Final:SRM) * ISS installation (Review 7/19) * High power laser installation === Progress of commissioning === * X arm commissioning * End X IM 83K * Investigation of the noise in the new oplev light source * Investigation of the TMSX beam shape * Y arm commissioning * End Y : Pumping down ongoing, there are still some leak, but we will continue the pumping down * Center area commissioning * Suspension health check Type-Bp's * Oplev upgrade : Done * PRM and PR3 mostly done, PR2 there are some homework * Mid-size baffle : Partially done, need to move to final position * Investigation of the X-arm fiber noise cancellation * Xarm : became stable -> Same treatment to Yarm * Study for installation of the new laser * Set inside the PSL room this week * OMC investigation * SRM replacement : Done * Power budget : Done * Beam profile measurement : This weeek === Interesting data === * X arm cavity * Both IR and GR * Glitch investigation of the ITMX ADC * Glitch investigation of the MN oplev light source * Y arm commissioning * Both IR and GR * Center area commissioning * Main IR * ALS * IMC (Input Mode Cleaner) * ASC (Alignment Sensing and Control) done * Long term stability check * Beam power, beam position, oplev monitoring * Glitch investigation * Temperature dependence * Relationship between PSL room * With PEM channels * (Hammering test?) * OMC * Invesigation will continue after closing the center area * Because the BS is too fluctuate, it became difficult to investigate