Line 7: | Line 7: |
* (In case of no trouble) * 7/11 - 7/22 Suspension commissioning Type-B and PR2 * 7/25 - 7/29 Acceptance check ~PR2 * 8/1 - 8/5 Closing the center area ~PR2 * 8/8 - 8/19 (Including Obon) Acceptance check ~SRM * 8/22 - 8/26 Closing the center area ~SRM * 8/29 - 9/2 Leak test * Mid size baffle installation (Final:SRM) * ISS installation (Review 7/19) * High power laser installation |
* Overall schedule * 7/11 - 8/12 Suspension commissioning Type-B * 8/1 - 8/5 Acceptance check PRM~PR2 * 8/22 - 8/26 Closing the center area PRM~PR2 * 8/13 - 8/19 Acceptance check BS~SRM * 8/29 - 9/2 Closing the center area BS~SRM * 9/5 - 9/9 Leak test * ?? Acceptance check IMC~PRM |
Line 20: | Line 17: |
* Some delay from * Beam dump around IFI * SR3, SRM mid-size baffle final check |
|
Line 23: | Line 24: |
* Suspension check with cryogenic temperature | |
Line 25: | Line 27: |
* Investigation of the ADC noise | |
Line 27: | Line 30: |
* End Y : Pumping down ongoing, there are still some leak, but we will continue the pumping down | * Pumping down ongoing * IY cooling : This week |
Line 30: | Line 34: |
* Suspension health check Type-Bp's * Oplev upgrade : Done * PRM and PR3 mostly done, PR2 there are some homework * Mid-size baffle : Partially done, need to move to final position * Investigation of the X-arm fiber noise cancellation * Xarm : became stable -> Same treatment to Yarm |
* Mid-size baffle SRM : Partially done, need to move to final position |
Line 37: | Line 38: |
* Set inside the PSL room this week * OMC investigation * SRM replacement : Done * Power budget : Done * Beam profile measurement : This weeek |
* Set inside the PSL room * Chiller problem * REFL table investigation * Check power budget * Beam dump around IFI * Many ghost beam * beam dumper from reflection beam of the PRM * ALS CARM/DARM * Just started the investigation |
KAGRA Commissioning status at DET meeting
- Date : 2022/07/11
Overall schedule
- Overall schedule
- 7/11 - 8/12 Suspension commissioning Type-B
- 8/1 - 8/5 Acceptance check PRM~PR2
- 8/22 - 8/26 Closing the center area PRM~PR2
- 8/13 - 8/19 Acceptance check BS~SRM
- 8/29 - 9/2 Closing the center area BS~SRM
- 9/5 - 9/9 Leak test
- ?? Acceptance check IMC~PRM
Progress of commissioning
- Some delay from
- Beam dump around IFI
- SR3, SRM mid-size baffle final check
- X arm commissioning
- End X IM 83K
- Suspension check with cryogenic temperature
- Investigation of the noise in the new oplev light source
- Investigation of the TMSX beam shape
- Investigation of the ADC noise
- End X IM 83K
- Y arm commissioning
- Pumping down ongoing
- IY cooling : This week
- Center area commissioning
- Mid-size baffle SRM : Partially done, need to move to final position
- Study for installation of the new laser
- Set inside the PSL room
- Chiller problem
- REFL table investigation
- Check power budget
- Beam dump around IFI
- Many ghost beam
- beam dumper from reflection beam of the PRM
- ALS CARM/DARM
- Just started the investigation
Interesting data
- X arm cavity
- Both IR and GR
- Glitch investigation of the ITMX ADC
- Glitch investigation of the MN oplev light source
- Y arm commissioning
- Both IR and GR
- Center area commissioning
- Main IR
- ALS
- IMC (Input Mode Cleaner)
- ASC (Alignment Sensing and Control) done
- Long term stability check
- Beam power, beam position, oplev monitoring
- Glitch investigation
- Temperature dependence
- Relationship between PSL room
- With PEM channels
- (Hammering test?)
- OMC
- Invesigation will continue after closing the center area
- Because the BS is too fluctuate, it became difficult to investigate