Differences between revisions 1 and 2
Revision 1 as of 2022-07-25 06:45:22
Size: 2090
Comment:
Revision 2 as of 2022-07-25 06:51:00
Size: 1983
Comment:
Deletions are marked like this. Additions are marked like this.
Line 7: Line 7:
 * (In case of no trouble)
  * 7/11 - 7/22 Suspension commissioning Type-B and PR2
  * 7/25 - 7/29 Acceptance check ~PR2
  * 8/1 - 8/5 Closing the center area ~PR2
  * 8/8 - 8/19 (Including Obon) Acceptance check ~SRM
  * 8/22 - 8/26 Closing the center area ~SRM
  * 8/29 - 9/2 Leak test

  * Mid size baffle installation (Final:SRM)
  * ISS installation (Review 7/19)
  * High power laser installation
 * Overall schedule
  * 7/11 - 8/12 Suspension commissioning Type-B
  * 8/1 - 8/5 Acceptance check PRM~PR2
  * 8/22 - 8/26 Closing the center area PRM~PR2
  * 8/13 - 8/19 Acceptance check BS~SRM
  * 8/29 - 9/2 Closing the center area BS~SRM
  * 9/5 - 9/9 Leak test
  * ?? Acceptance check IMC~PRM
Line 20: Line 17:
   * Some delay from
  * Beam dump around IFI
  * SR3, SRM mid-size baffle final check
Line 23: Line 24:
   * Suspension check with cryogenic temperature
Line 25: Line 27:
  * Investigation of the ADC noise
Line 27: Line 30:
  * End Y : Pumping down ongoing, there are still some leak, but we will continue the pumping down   * Pumping down ongoing
  * IY cooling : This week
Line 30: Line 34:
  * Suspension health check Type-Bp's
   * Oplev upgrade : Done
   * PRM and PR3 mostly done, PR2 there are some homework
  * Mid-size baffle : Partially done, need to move to final position
  * Investigation of the X-arm fiber noise cancellation
   * Xarm : became stable -> Same treatment to Yarm

  * Mid-size baffle SRM : Partially done, need to move to final position
Line 37: Line 38:
   * Set inside the PSL room this week
  * OMC investigation
   * SRM replacement : Done
   * Power budget : Done
   * Beam profile measurement : This weeek
   * Set inside the PSL room
   * Chiller problem

 * REFL table investigation
  * Check power budget

 * Beam dump around IFI
  * Many ghost beam
  * beam dumper from reflection beam of the PRM

 * ALS CARM/DARM
  * Just started the investigation

KAGRA Commissioning status at DET meeting

  • Date : 2022/07/11

Overall schedule

  • Overall schedule
    • 7/11 - 8/12 Suspension commissioning Type-B
    • 8/1 - 8/5 Acceptance check PRM~PR2
    • 8/22 - 8/26 Closing the center area PRM~PR2
    • 8/13 - 8/19 Acceptance check BS~SRM
    • 8/29 - 9/2 Closing the center area BS~SRM
    • 9/5 - 9/9 Leak test
    • ?? Acceptance check IMC~PRM

Progress of commissioning

  • Some delay from
    • Beam dump around IFI
    • SR3, SRM mid-size baffle final check
  • X arm commissioning
    • End X IM 83K
      • Suspension check with cryogenic temperature
    • Investigation of the noise in the new oplev light source
    • Investigation of the TMSX beam shape
    • Investigation of the ADC noise
  • Y arm commissioning
    • Pumping down ongoing
    • IY cooling : This week
  • Center area commissioning
    • Mid-size baffle SRM : Partially done, need to move to final position
    • Study for installation of the new laser
      • Set inside the PSL room
      • Chiller problem
  • REFL table investigation
    • Check power budget
  • Beam dump around IFI
    • Many ghost beam
    • beam dumper from reflection beam of the PRM
  • ALS CARM/DARM
    • Just started the investigation

Interesting data

  • X arm cavity
    • Both IR and GR
    • Glitch investigation of the ITMX ADC
    • Glitch investigation of the MN oplev light source
  • Y arm commissioning
    • Both IR and GR
  • Center area commissioning
    • Main IR
    • ALS
    • IMC (Input Mode Cleaner)
      • ASC (Alignment Sensing and Control) done
      • Long term stability check
        • Beam power, beam position, oplev monitoring
      • Glitch investigation
      • Temperature dependence
      • Relationship between PSL room
      • With PEM channels
      • (Hammering test?)
    • OMC
      • Invesigation will continue after closing the center area
      • Because the BS is too fluctuate, it became difficult to investigate

KAGRA/Subgroups/DET/Meeting/220725 (last edited 2022-07-25 06:51:00 by TakaakiYokozawa)