== KAGRA Commissioning status at DET meeting == * Date : 2022/07/11 === Overall schedule === * Overall schedule * 7/11 - 8/12 Suspension commissioning Type-B * 8/1 - 8/5 Acceptance check PRM~PR2 * 8/22 - 8/26 Closing the center area PRM~PR2 * 8/13 - 8/19 Acceptance check BS~SRM * 8/29 - 9/2 Closing the center area BS~SRM * 9/5 - 9/9 Leak test * ?? Acceptance check IMC~PRM === Progress of commissioning === * Some delay from * Beam dump around IFI * SR3, SRM mid-size baffle final check * X arm commissioning * End X IM 83K * Suspension check with cryogenic temperature * Investigation of the noise in the new oplev light source * Investigation of the TMSX beam shape * Investigation of the ADC noise * Y arm commissioning * Pumping down ongoing * IY cooling : This week * Center area commissioning * Mid-size baffle SRM : Partially done, need to move to final position * Study for installation of the new laser * Set inside the PSL room * Chiller problem * REFL table investigation * Check power budget * Beam dump around IFI * Many ghost beam * beam dumper from reflection beam of the PRM * ALS CARM/DARM * Just started the investigation === Interesting data === * X arm cavity * Both IR and GR * Glitch investigation of the ITMX ADC * Glitch investigation of the MN oplev light source * Y arm commissioning * Both IR and GR * Center area commissioning * Main IR * ALS * IMC (Input Mode Cleaner) * ASC (Alignment Sensing and Control) done * Long term stability check * Beam power, beam position, oplev monitoring * Glitch investigation * Temperature dependence * Relationship between PSL room * With PEM channels * (Hammering test?) * OMC * Invesigation will continue after closing the center area * Because the BS is too fluctuate, it became difficult to investigate