Line 3: Line 3:
 * Date : 2022/07/11  * Date : 2022/08/08
Line 9: Line 9:
  * 8/1 - 8/5 Acceptance check PRM~PR2   * 8/5 Acceptance check PRM, PR2, PR3 suspensions

KAGRA Commissioning status at DET meeting

  • Date : 2022/08/08

Overall schedule

  • Overall schedule
    • 7/11 - 8/12 Suspension commissioning Type-B
    • 8/5 Acceptance check PRM, PR2, PR3 suspensions
    • 8/22 - 8/26 Closing the center area PRM~PR2
    • 8/13 - 8/19 Acceptance check BS~SRM
    • 8/29 - 9/2 Closing the center area BS~SRM
    • 9/5 - 9/9 Leak test
    • ?? Acceptance check IMC~PRM

Progress of commissioning

  • Some delay from
    • Beam dump around IFI
    • SR3, SRM mid-size baffle final check
  • X arm commissioning
    • End X IM 83K
      • Suspension check with cryogenic temperature
    • Investigation of the noise in the new oplev light source
    • Investigation of the TMSX beam shape
    • Investigation of the ADC noise
  • Y arm commissioning
    • Pumping down ongoing
    • IY cooling : This week
  • Center area commissioning
    • Mid-size baffle SRM : Partially done, need to move to final position
    • Study for installation of the new laser
      • Set inside the PSL room
      • Chiller problem
  • REFL table investigation
    • Check power budget
  • Beam dump around IFI
    • Many ghost beam
    • beam dumper from reflection beam of the PRM
  • ALS CARM/DARM
    • Just started the investigation

Interesting data

  • X arm cavity
    • Both IR and GR
    • Glitch investigation of the ITMX ADC
    • Glitch investigation of the MN oplev light source
  • Y arm commissioning
    • Both IR and GR
  • Center area commissioning
    • Main IR
    • ALS
    • IMC (Input Mode Cleaner)
      • ASC (Alignment Sensing and Control) done
      • Long term stability check
        • Beam power, beam position, oplev monitoring
      • Glitch investigation
      • Temperature dependence
      • Relationship between PSL room
      • With PEM channels
      • (Hammering test?)
    • OMC
      • Invesigation will continue after closing the center area
      • Because the BS is too fluctuate, it became difficult to investigate