== KAGRA Commissioning status at DET meeting == * Date : 2022/08/08 === Overall schedule === * Overall schedule * 7/11 - 8/12 Suspension commissioning Type-B * 8/5 Acceptance check PRM, PR2, PR3 suspensions * 8/19 Acceptance check BS~SRM * X/XX Acceptance check interferometer PR3-SR3 * 8/22 - 8/26 Closing the center area PRM~PR2 * 8/29 - 9/2 Closing the center area BS~SRM * 9/5 - 9/9 Leak test * Y/YY Acceptance check IMC~PRM === Progress of commissioning === * X arm commissioning * End X IM 81K * Monitor, eigen-frequency, transfer function check [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=14196|poster]] * Investigation of the noise in the new oplev light source * Investigation of the ADC noise * Y arm commissioning * Pumping down ongoing * Installed the ion pums to IXC and IYC * IY duct shield cooling (8/5- Started) * Beam dump around IFI * Many ghost beam * beam dumper from reflection beam of the PRM * Temperature monitor * ALS CARM/DARM * ALS CARM/DARM lock succeeded * Calibration confirmation * Transfer function measurement Type-A suspension * Noise budget * MICH 3f lock * Actuation efficiency measurement * Discussion of closing center area * Oplev pylon * Beam duct re-installation * New gate valve * Closing chambers around BS area === Interesting data === * X arm cavity * Both IR and GR * Glitch investigation of the ITMX ADC * Glitch investigation of the MN oplev light source * Y arm commissioning * Both IR and GR * Center area commissioning * MICH 3f lock * Check the lock information * ALS CARM/DARM * Check the lock information * IMC (Input Mode Cleaner) * ASC (Alignment Sensing and Control) done * Long term stability check * Beam power, beam position, oplev monitoring * Glitch investigation * Temperature dependence * Relationship between PSL room * With PEM channels * (Hammering test?) * OMC * Invesigation will continue after closing the center area * Because the BS is too fluctuate, it became difficult to investigate