KAGRA Commissioning status at DET meeting

  • Date : 2022/08/22

Overall schedule

  • Overall schedule
    • 7/11 - 8/19 Suspension commissioning Type-B
    • 8/22 - 8/26 Closing the center area PRM~PR2
    • 8/29 - 9/5 Closing the center area BS~SRM
    • 9/6 - pumping down
    • 8/5 Acceptance check PRM, PR2, PR3 suspensions
    • 8/19 Acceptance check BS, SR2, SR3, SRM
    • 8/22 Acceptance check mid-size baffules
    • 8/26 Acceptance check interferometer
    • Y/YY Acceptance check IMC~PRM

Progress of commissioning

  • X arm commissioning
    • End X IM 81K
    • Investigation of the noise in the new oplev light source
    • Investigation of the ADC noise
  • Y arm commissioning
    • Pumping down ongoing
    • Installed the ion pums to IXC and IYC
    • IY duct shield cooling (8/5- Started)
  • Beam dump around IFI
    • Many ghost beam
    • beam dumper from reflection beam of the PRM
    • Temperature monitor
  • ALS CARM/DARM
    • ALS CARM/DARM lock succeeded
    • Calibration confirmation
    • Transfer function measurement Type-A suspension
    • Noise budget
    • Now the noise level is limited by the ALS after fiber noise cancellation
  • Find IR resonance improved
  • MICH 3f lock
    • Actuation efficiency measurement
  • TCam analysis
    • Find the beam position
  • OMC alignment
  • Discussion of closing center area
    • Oplev pylon
    • Beam duct re-installation
    • New gate valve
    • Closing chambers around BS area

Interesting data

  • X arm cavity
    • Both IR and GR
    • Glitch investigation of the ITMX ADC
    • Glitch investigation of the MN oplev light source
  • Y arm commissioning
    • Both IR and GR
  • Center area commissioning
    • MICH 3f lock
      • Check the lock information
    • ALS CARM/DARM
      • Check the lock information
    • IMC (Input Mode Cleaner)
      • ASC (Alignment Sensing and Control) done
      • Long term stability check
        • Beam power, beam position, oplev monitoring
      • Glitch investigation
      • Temperature dependence
      • Relationship between PSL room
      • With PEM channels
      • (Hammering test?)
    • OMC
      • Invesigation will continue after closing the center area
      • Because the BS is too fluctuate, it became difficult to investigate

KAGRA/Subgroups/DET/Meeting/220822 (last edited 2022-08-22 18:56:38 by HirotakaYuzurihara)