* Overall schedule * 10/04 Start the pumping down * After fixing the large leak * 2e-5 Pa at BS * 2e-4 Pa at IMM * Interferometer overall * FPMI lock succeeded! * DARM(AS17), CARM(REFL45), MICH(REFL51->POP17) * Latest sensitivity [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=22422|klog22422]] * Calibration evaluation * Control filter optimization * Interferometer characterization * X arm commissioning * End X IM 81K * We will start the noise budget of the new oplev again * Y arm commissioning * IY duct shield cooling * TMSY vacuum preparation * New high power laser * Chiller preparation * Turned on * Prepared the spared lens * ISS * Characterization is ongoing * ASC preparation * WFS settings, optics optimization