⇤ ← Revision 1 as of 2022-12-02 12:27:18
Size: 1188
Comment:
|
Size: 1398
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
* OMC : In air, finalize will be performed this week. * 22nd Nov: Close chamber, start pumping down |
* OMC : on 22 Nov, closed chamber, started pumping down [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=23002|klog#23002]] * but, mall leak was found [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=23024|klog#23024]] |
Line 8: | Line 8: |
* ETMY cooling down will start from 15th Nov. | * ETMY cooling down will start from 29th Nov. [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=23078|klog#23078]] |
Line 12: | Line 12: |
* 16:00- everyday | * 16:00- everyday (sometimes 11:00-) |
Line 32: | Line 32: |
* IY duct shield cooling | * IY duct shield cooling * EY duct shield cooling |
- 221207
- Overall schedule
- All leak test at center area was performed
OMC : on 22 Nov, closed chamber, started pumping down klog#23002
but, mall leak was found klog#23024
- TMSY : In vac, leak test done, opened the gate valve after 15th Nov.
ETMY cooling down will start from 29th Nov. klog#23078
- All leak test at center area was performed
- Interferometer overall
- Initial alignment experiment
- 16:00- everyday (sometimes 11:00-)
- PRMI lock trial
- Search the good alignment
- ADS engaged and alignment of the IMMT1,2 and PRM
- Search the good alignment
- FPMI lock succeeded
DARM(AS17), CARM(REFL45), MICH(REFL51->POP17)
Latest sensitivity klog22097
- Calibration evaluation
- Control filter optimization
- Interferometer characterization
- X arm commissioning
- End X IM 85K
- We will start the noise budget of the new oplev again
- OMC ASC using the Xend test mass
- Signal was detected in OMC PD
- Y arm commissioning
- IY duct shield cooling
- EY duct shield cooling
- New high power laser
- PMC locked
- ISS
- Control loop done
- Characterization is ongoing
- ASC preparation
- Sensing matrix measurements
- Initial alignment experiment