Size: 1205
Comment:
|
Size: 1181
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 12: | Line 12: |
* FPMI lock * Lock enable * Trial for DC readout with ISS control |
* FPMI lock * Lock enable * Trial for DC readout with ISS control |
Line 16: | Line 16: |
* PRFPMI lock trial * PRMI lock stable * Establish the initial alignment * Bottle neck is the noise level of ALS * It made difficult to hand over from GR to IR |
* PRFPMI lock trial * PRMI lock stable * Establish the initial alignment * Bottle neck is the noise level of ALS * It made difficult to hand over from GR to IR |
Line 22: | Line 22: |
* ALS noise hunting * We found ondotori was one of the noise which made twin glitch * 0.4 Hz unknown peak |
* ALS noise hunting * We found ondotori was one of the noise which made twin glitch * 0.4 Hz unknown peak |
Line 26: | Line 26: |
* ASC implementation * Evaluate offset map * Trial of the implementation of the ASC loop |
* ASC implementation * Evaluate offset map * Trial of the implementation of the ASC loop |
Line 30: | Line 30: |
* OMC status * Pumping down : ongoing * We succeeded to lock the OMC LSC and ASC * Implemented the OMC ASC using beacom from the ETMX drum head mode |
* OMC status * Pumping down : ongoing * We succeeded to lock the OMC LSC and ASC * Implemented the OMC ASC using beacom from the ETMX drum head mode |
Line 35: | Line 35: |
* Suspension commissioning * Check the long term stability of the suspensions with the control loop for the observation mode * Investigating the ACC, geophone, seismometer and LVDT for reducing the low frequency fluctuation |
* Suspension commissioning * Check the long term stability of the suspensions with the control loop for the observation mode * Investigating the ACC, geophone, seismometer and LVDT for reducing the low frequency fluctuation |
Line 39: | Line 39: |
* ISS/High power laser * ISS characterization is ongoing * High power laser : Check the stability of IMC LSC lock |
* ISS/High power laser * ISS characterization is ongoing * High power laser : Check the stability of IMC LSC lock |
- 221214
- Overall schedule
- FPMI lock
- PRFPMI lock trial
- ALS noise hunting
- ASC implementation
- OMC status
- Suspension commissioning
- ISS/High power laser
- FPMI lock
- Lock enable
- Trial for DC readout with ISS control
- PRFPMI lock trial
- PRMI lock stable
- Establish the initial alignment
- Bottle neck is the noise level of ALS
- It made difficult to hand over from GR to IR
- ALS noise hunting
- We found ondotori was one of the noise which made twin glitch
- 0.4 Hz unknown peak
- ASC implementation
- Evaluate offset map
- Trial of the implementation of the ASC loop
- OMC status
- Pumping down : ongoing
- We succeeded to lock the OMC LSC and ASC
- Implemented the OMC ASC using beacom from the ETMX drum head mode
- Suspension commissioning
- Check the long term stability of the suspensions with the control loop for the observation mode
- Investigating the ACC, geophone, seismometer and LVDT for reducing the low frequency fluctuation
- ISS/High power laser
- ISS characterization is ongoing
- High power laser : Check the stability of IMC LSC lock