* Overall schedule * End of July - End of August : Pumping down center area * Sep - Commissioning * X arm commissioning * Both IR and GR cavity lock keeping * IX : Cooling down the duct shield TM~250 K * EX : Cooling down the duct and two radiation shield TM~110K * Finesse and TM position by TCam are ongoing * TMSX optical table characterization : early July : After this, we can start ASC * Y arm commissioning * Pumping down started * EY has leak point, we will open the chamber soon * IR and GR lock succeeded! * Center area commissioning * Main IR * Table configuration : ongoing * IFO refl table * POP (Pick of PR2) table * POP forward QPD installed * Interesting channel for X arm IR lock : [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=14080|JGWDoc14080]] * Mirror cleaning(first contact) and mid-size baffle installation * PR2 : Installed * SR2 : Installed * BS : Installed * PRM : Installed * PR3 : First contact (maybe) done * SR3 : Not yet * SRM : Not yet (When replacement?) * IMC (Input Mode Cleaner) * ASC (Alignment Sensing and Control) done * Suspension commissioning : ongoing * PR's suspension middle of June - end of June (two weeks) * OMC installation : done * Some unexpected glitch : circuit? * Alignment : partially done : BS fluctuation large and SRM replacement * TF measurement : ongoing * High power laser * Accepted to install to KAGRA site * When exchange the laser source : Unknown * ISS (Intensity Stabilization System) installation : unknown * Must item before closing chamber