* Any thing else? * Progress report from Kamioka * Rack preparation. (Miyo) * By the way, do we have a conversion board for ADC to D-sub from BNC? * Software preparation (Pil-Jong) * Any thing else? * Communication tool for the PEM injection: Slack (Miyo) * github for management of the PEM project (Miyo) |
Detchar Meeting 20180123
Participants
Agenda & Minutes
See also http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/DET/Meet/Agenda20180123
- Report from Extended Chief meeting on Jan. 22nd (Hayama)
- Experiment after bKAGRA phase1 run will be start around the end of April (on Apr. 30th??).
- 5th and 6th day will be assigned to PEM injection?
- Any thing else?
- Progress report from Hongo
- Calibration of the toy pendulum system (injection target in rehearsal) has beed done.
- We checked two demo-unit of small accelerometer (FG-142 and 2002E).
- We will buy FG-142 in next fiscal year.
- Miyazaki-kun, who is a new grad. student of Ando lab., has started mede analog circuit for magnetometer.
- Magnet wire for large coil (~100 m) arrived. Large wooden bobbin will arrive in the end of Jan. (or the beginning of Feb.)
- Connector parts for amplifier (QSC RMX5050a) arrived.
- We obtained power supply connector used in KAGRA. However, we don't have pins.
- Maybe we will make it in Kamioka in the first day of the rehearsal. Or will anyone come to Ochi-kun's master thesis defense and take the pins?
- Any thing else?
- Progress report from Kamioka
- Rack preparation. (Miyo)
- By the way, do we have a conversion board for ADC to D-sub from BNC?
- Software preparation (Pil-Jong)
- Any thing else?
- Rack preparation. (Miyo)
- Communication tool for the PEM injection: Slack (Miyo)
- github for management of the PEM project (Miyo)
Action items