== Current Status == 1. Waiting for shipping the sensors. -> Implementation of sensors. 2. Drawing the box for Raspeberry Pi and sensors 3. Software: almost done. (database) |
|
Line 13: | Line 18: |
4. Magnetic field ([[http://www.rohm.co.jp/web/japan/news-detail?news-title=2015-06-17_ad_mi&defaultGroupId=false|BM1422GMV: Rohm]]) 5. Water-proof Camera |
4. Magnetic field ([[http://www.aichi-mi.com/topics/%E9%9B%BB%E5%AD%90%E3%82%B3%E3%83%B3%E3%83%91%E3%82%B9/ami306r%E3%82%B3%E3%83%B3%E3%83%91%E3%82%B9/|AMI306R: Aichi Steel]]) |
Line 18: | Line 22: |
Updated information: initial install number at the network point w/ wired LAN is 6 for each arm. |
|
Line 26: | Line 32: |
|| January 2017 || Building up all sensors is started. || || February 2017 || Test at ESPEC https://www.espec.co.jp/products/trustee/ || || March 2017 || Install start at Kamioka || || May 2017 || Install end at Kamioka || |
|| January 2017 || Building up all sensors is started. || || February 2017 || Test at ESPEC https://www.espec.co.jp/products/trustee/ || || March 2017 || Install start at Kamioka || || May 2017 || Install end at Kamioka || |
Current Status
Waiting for shipping the sensors. -> Implementation of sensors.
- Drawing the box for Raspeberry Pi and sensors
- Software: almost done. (database)
Aim
To monitor the tunnel environment except the center and end ares.
Construction
- Sensor (Raspberry Pi 3 based + EPICS)
- Monitor map system (software: EPICS based?)
Monitor map
We should decide the required sampling rate and resolution. Target: 10 Hz sampling
Temperature (SHT-25)
Humidity (SHT-25)
Air pressure (BM1383GLV: Rohm)
Magnetic field (AMI306R: Aichi Steel)
How many?
Every 200 m, we put the sensor. The estimated number of the sensors is 30.
Updated information: initial install number at the network point w/ wired LAN is 6 for each arm.
Special Meeting
Meeting Information w/ Miyo, Yamamoto, and Shikano on 10/27/2016
Schedule
October 2016 |
Test the sensors at IMS (#3) w Preliminary sensor |
November 2016 |
First trial sensors from IMS to Kamioka (#3) w Preliminary sensor |
December 2016 |
Adjustment / EPICS developmenet |
January 2017 |
Building up all sensors is started. |
February 2017 |
Test at ESPEC https://www.espec.co.jp/products/trustee/ |
March 2017 |
Install start at Kamioka |
May 2017 |
Install end at Kamioka |