Current Status
Waiting for shipping the sensors. -> Implementation of sensors.
- Drawing the box for Raspeberry Pi and sensors
- Software: almost done. (database)
Aim
To monitor the tunnel environment except the center and end ares.
Construction
- Sensor (Raspberry Pi 3 based + EPICS)
- Monitor map system (software: EPICS based?)
Monitor map
We should decide the required sampling rate and resolution. Target: 10 Hz sampling
Temperature (SHT-25)
Humidity (SHT-25)
Air pressure (BM1383GLV: Rohm)
Magnetic field (AMI306R: Aichi Steel)
How many?
Every 200 m, we put the sensor. The estimated number of the sensors is 30.
Updated information: initial install number at the network point w/ wired LAN is 6 for each arm.
Special Meeting
Meeting Information w/ Miyo, Yamamoto, and Shikano on 10/27/2016
Schedule
October 2016 |
Test the sensors at IMS (#3) w Preliminary sensor |
November 2016 |
First trial sensors from IMS to Kamioka (#3) w Preliminary sensor |
December 2016 |
Adjustment / EPICS developmenet |
January 2017 |
Building up all sensors is started. |
February 2017 |
Test at ESPEC https://www.espec.co.jp/products/trustee/ |
March 2017 |
Install start at Kamioka |
May 2017 |
Install end at Kamioka |