 * Boot server
  * --(PC setup)-- (2013/6/12 - 2013/6/18)
  * --(kernel to 3.0.8)-- (2013/6/6 - 2013/7/10)
=== Common ===

 * Timing
  * GPS antenna (2013/4/8 - 2013/9/25 done)
  * IRG-B chassis (2013/4/8 - 2013/9/25 done)


=== A rack ===

 * NAT1
  * --(PC setup)-- (2013/4/4 - 2013/4/10 done)
  * --(NAT setup)-- (2013/5/1 - 2013/5/8 done)
  * DHCP
  * DNS

=== N rack ===

 * NAT2 (P:2014/8/1 - 2014/8/31)

 * Boot server (2013/6/6 - P:2013/12/31)
  * --(PC setup)-- (2013/6/12 - 2013/6/18 done)
  * --(kernel to 3.0.8)-- (2013/6/6 - 2013/7/10 done)
  * Release daqd (P:2013/12/10 - P:2013/12/20)
  * Release nds (P:2013/12/20 - 2013/12/31)
Line 8: Line 29:
 * Data Concentrator (2013/12/10-2013/12/20) === D rack ===

 * --(10Gb switch)-- (2013/7/20 - 2013/7/22 done)

* Data Concentrator (2013/12/10 - P:2013/12/20)
Line 33: Line 58:
 * --(Hardware setup)-- (2013/5/31 - 2013/5/31 done)
 * Connection to FEFS (P:2014/2/1 - 2014/2/28)
  * --(Hardware setup)-- (2013/5/31 - 2013/5/31 done)
  * Connection to FEFS (P:2014/2/1 - 2014/2/28)
Line 36: Line 61:
 * Real-time front end 1
  * --(RT PC setup)--  (??/??/2013 done)
  * --(IO chassis)-- (??/??/2013 done)
  * --(Connection to boot server)--
=== C rack ===

 * --(
Real-time front end 1)-- (2013/4/9 - 2013/12/3 done)
  * --(RT PC setup)-- (2013/4/9 - 2013/4/9 done)
  * --(IO chassis)-- (2013/7/16 - 2013/7/17 done)
  * --(Connection to boot server)-- (2013/4/9 - 2013/6/6 done)
Line 43: Line 70:
 * Real-time front end 2
  * --(RT PC setup)-- (2013/4/10 - 2013/??/?? done)
  * --(IO chassis)-- (2013/11/8 - 2013/??/?? done)
  * --(Connection to boot server)--
 * --(Real-time front end 2)-- (2013/4/10 - 2013/12/3 done)
  * --(RT PC setup)-- (2013/4/10 - 2013/4/10 done)
  * --(IO chassis)-- (2013/11/8 - 2013/11/11 done)
  * --(Connection to boot server)-- (2013/6/6 - 2013/6/6 done)
Line 51: Line 78:
 * --(Real-time front end 3)-- ((2013/4/9 - 2013/12/4 done))
  * --(RT PC setup)-- (2013/4/9 - 2013/12/4 done)
 * --(Real-time front end 3)-- (2013/4/9 - 2013/12/5 done)
  * --(RT PC setup)-- (2013/4/9 - 2013/4/9 done)
Line 59: Line 86:
=== Client WS 1 ===
 * --(PC setup)-- (??/??/2013 done)
 * External backup HDD setup
 * backup completed HDD
=== Desk ===
Line 64: Line 88:
=== Network ===
 * --(10Gb switch)-- (??/??/2013 done)
 * --(Dolphin newtwork)-- (11/12/2013 done)
 * Client WS 1
  * --(PC setup)-- (2013/4/10 - 2013/4/25 done)
  * External backup HDD setup
  * backup completed HDD
Line 68: Line 93:
=== Timing ===
 * --(GPS antenna)-- (??/??/2013 done)
 * IRG-B card

Common

  • Timing
    • GPS antenna (2013/4/8 - 2013/9/25 done)
    • IRG-B chassis (2013/4/8 - 2013/9/25 done)

A rack

  • NAT1
    • PC setup (2013/4/4 - 2013/4/10 done)

    • NAT setup (2013/5/1 - 2013/5/8 done)

    • DHCP
    • DNS

N rack

  • NAT2 (P:2014/8/1 - 2014/8/31)
  • Boot server (2013/6/6 - P:2013/12/31)
    • PC setup (2013/6/12 - 2013/6/18 done)

    • kernel to 3.0.8 (2013/6/6 - 2013/7/10 done)

    • Release daqd (P:2013/12/10 - P:2013/12/20)
    • Release nds (P:2013/12/20 - 2013/12/31)
  • File server (P:12/15/2013 - 12/25/2013)
    • PC setup (P:12/15/2013 - 12/20/2013)

D rack

  • 10Gb switch (2013/7/20 - 2013/7/22 done)

  • Data Concentrator (2013/12/10 - P:2013/12/20)
    • PC setup (2013/12/10-2013/12/10)
    • Myrinet card1 set (2013/12/10 - 2013/12/10 done)

    • Myrinet card2 set (2013/12/10 - 2013/12/10 done)

    • HDD copy (P:2013/12/10 - 2013/12/10)
    • host name change (P:2013/12/10 - 2013/12/11)
    • daqd running (P:2013/12/11 - 2013/12/15)
  • NDS 1 (P:2013/12/20 - 2013/12/31)
    • PC setup
  • NDS 2 (P:2014/3/1 - 2014/3/31)
    • PC setup
  • Frame Writer 1 (P:2014/1/5 - 2014/1/20)
    • PC setup
  • Frame Writer 2 (P:2014/1/5 - 2014/1/20)
    • PC setup
  • Local storage 1
    • Hardware setup (2013/5/31 - 2013/5/31 done)

    • Connection to FEFS (P:2014/2/1 - 2014/2/28)
  • Local storage 2
    • Hardware setup (2013/5/31 - 2013/5/31 done)

    • Connection to FEFS (P:2014/2/1 - 2014/2/28)

C rack

  • Real-time front end 1 (2013/4/9 - 2013/12/3 done)

    • RT PC setup (2013/4/9 - 2013/4/9 done)

    • IO chassis (2013/7/16 - 2013/7/17 done)

    • Connection to boot server (2013/4/9 - 2013/6/6 done)

    • IRIG-B synchronization (2013/11/12 - 2013/12/3 done)

    • DAQ connection (2013/11/8 - 2013/11/11 done)

  • Real-time front end 2 (2013/4/10 - 2013/12/3 done)

    • RT PC setup (2013/4/10 - 2013/4/10 done)

    • IO chassis (2013/11/8 - 2013/11/11 done)

    • Connection to boot server (2013/6/6 - 2013/6/6 done)

    • IRIG-B synchronization (2013/11/12 - 2013/12/3 done)

    • DAQ connection (2013/11/8 - 2013/11/11 done)

    • Dolphin connection (2013/11/12 - 2013/12/3 done)

  • Real-time front end 3 (2013/4/9 - 2013/12/5 done)

    • RT PC setup (2013/4/9 - 2013/4/9 done)

    • IO chassis (2013/11/12 - 2013/12/4 done)

    • Connection to boot server (2013/12/3 - 2013/12/3 done)

    • IRIG-B synchronization (2013/12/3 - 2013/12/3 done)

    • DAQ connection (2013/12/3 - 2013/12/3 done)

    • RFM connection (2013/12/3 - 2013/12/5 done)

Desk

  • Client WS 1
    • PC setup (2013/4/10 - 2013/4/25 done)

    • External backup HDD setup
    • backup completed HDD

Documentation