Common
- Timing
- GPS antenna (2013/4/8 - 2013/9/25 done)
- IRG-B chassis (2013/4/8 - 2013/9/25 done)
A rack
- NAT1
PC setup (2013/4/4 - 2013/4/10 done)
NAT setup (2013/5/1 - 2013/5/8 done)
- DHCP
- DNS
N rack
- NAT2 (P:2014/8/1 - 2014/8/31)
- Boot server (2013/6/6 - P:2013/12/31)
PC setup (2013/6/12 - 2013/6/18 done)
kernel to 3.0.8 (2013/6/6 - 2013/7/10 done)
- Release daqd (P:2013/12/10 - P:2013/12/20)
- Release nds (P:2013/12/20 - 2013/12/31)
- File server (P:12/15/2013 - 12/25/2013)
- PC setup (P:12/15/2013 - 12/20/2013)
D rack
10Gb switch (2013/7/20 - 2013/7/22 done)
- Data Concentrator (2013/12/10 - P:2013/12/20)
- PC setup (2013/12/10-2013/12/10)
Myrinet card1 set (2013/12/10 - 2013/12/10 done)
Myrinet card2 set (2013/12/10 - 2013/12/10 done)
- HDD copy (P:2013/12/10 - 2013/12/10)
- host name change (P:2013/12/10 - 2013/12/11)
- daqd running (P:2013/12/11 - 2013/12/15)
- NDS 1 (P:2013/12/20 - 2013/12/31)
- PC setup
- NDS 2 (P:2014/3/1 - 2014/3/31)
- PC setup
- Frame Writer 1 (P:2014/1/5 - 2014/1/20)
- PC setup
- Frame Writer 2 (P:2014/1/5 - 2014/1/20)
- PC setup
- Local storage 1
Hardware setup (2013/5/31 - 2013/5/31 done)
- Connection to FEFS (P:2014/2/1 - 2014/2/28)
- Local storage 2
Hardware setup (2013/5/31 - 2013/5/31 done)
- Connection to FEFS (P:2014/2/1 - 2014/2/28)
C rack
Real-time front end 1 (2013/4/9 - 2013/12/3 done)
RT PC setup (2013/4/9 - 2013/4/9 done)
IO chassis (2013/7/16 - 2013/7/17 done)
Connection to boot server (2013/4/9 - 2013/6/6 done)
IRIG-B synchronization (2013/11/12 - 2013/12/3 done)
DAQ connection (2013/11/8 - 2013/11/11 done)
Real-time front end 2 (2013/4/10 - 2013/12/3 done)
RT PC setup (2013/4/10 - 2013/4/10 done)
IO chassis (2013/11/8 - 2013/11/11 done)
Connection to boot server (2013/6/6 - 2013/6/6 done)
IRIG-B synchronization (2013/11/12 - 2013/12/3 done)
DAQ connection (2013/11/8 - 2013/11/11 done)
Dolphin connection (2013/11/12 - 2013/12/3 done)
Real-time front end 3 (2013/4/9 - 2013/12/5 done)
RT PC setup (2013/4/9 - 2013/4/9 done)
IO chassis (2013/11/12 - 2013/12/4 done)
Connection to boot server (2013/12/3 - 2013/12/3 done)
IRIG-B synchronization (2013/12/3 - 2013/12/3 done)
DAQ connection (2013/12/3 - 2013/12/3 done)
RFM connection (2013/12/3 - 2013/12/5 done)
Desk
- Client WS 1
PC setup (2013/4/10 - 2013/4/25 done)
- External backup HDD setup
- backup completed HDD