Kokeyama, Uehara, Izumi, Huang, Prof. Wang, Prof. Sato, Prof. Ohkawa, Prof. Suzuki, Sugai, Fujii. Fujikawa
Line 6: Line 7:
Line 13: Line 15:
 * RefCav re-commissioning (with the PMC transmistting beam) was finished from the optics point of view  * RefCav re-commissioning (with the PMC transmitting beam) was finished from the optics point of view
Line 16: Line 18:
 * summary of the remaining tasks
 * OMC
 * summary of the remaining tasks (klog)
 * OMC - Working on the vac cable, PD mounts, OMC frame; started the isolation ratio of OFI
Line 19: Line 21:
 * High power testing is going in Hongo (Nakano, Tahara)
Line 22: Line 24:
 * Refcav pumping
 * RF sources (f1-f3) installation
 * RF distributor installation
 * Cabling 30m SMA from the IOO rack to PSL table
 * EOM/RAM
 * IMMT2 repairing will start
Line 24: Line 32:
 * from July 4th Uehara-san (high power EOM)
 * Fujii-kun (an undergrad student from Niigata U) July 4-11
 * from July 5th Uehara-san (high power EOM)
 * Fujii-kun (an undergrad student from Niigata U) July 5-11

Regular Meeting 0618

Participants

Kokeyama, Uehara, Izumi, Huang, Prof. Wang, Prof. Sato, Prof. Ohkawa, Prof. Suzuki, Sugai, Fujii. Fujikawa

Announcement

Schedule for Phase-2

Report from the Last 2 weeks

  • PMC installation, integration finished
  • RefCav re-commissioning (with the PMC transmitting beam) was finished from the optics point of view

  • IMC angular control loops were closed
  • Input pointing PZT mirrors were installed (pointing to the IMC)
  • summary of the remaining tasks (klog)
  • OMC - Working on the vac cable, PD mounts, OMC frame; started the isolation ratio of OFI
  • MZI - The 2nd IOO chassis, AA/AI filters were installed
  • High power testing is going in Hongo (Nakano, Tahara)

Plans for the coming 2 weeks

  • Refcav pumping
  • RF sources (f1-f3) installation
  • RF distributor installation
  • Cabling 30m SMA from the IOO rack to PSL table
  • EOM/RAM
  • IMMT2 repairing will start

Visitors

  • from July 5th Uehara-san (high power EOM)
  • Fujii-kun (an undergrad student from Niigata U) July 5-11

Absence

  • Kokeyama will be away from July 5 - 10

Commissioning Calendar

https://teamup.com/kswnmta8p18h6u1uab

Next meeting

  • July 17th