Size: 1041
Comment:
|
Size: 1479
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 4: | Line 4: |
Kokeyama, Uehara, Izumi, Huang, Prof. Wang, Prof. Sato, Prof. Ohkawa, Prof. Suzuki, Sugai, Fujii. Fujikawa | |
Line 6: | Line 7: |
Line 13: | Line 15: |
* RefCav re-commissioning (with the PMC transmistting beam) was finished from the optics point of view | * RefCav re-commissioning (with the PMC transmitting beam) was finished from the optics point of view |
Line 16: | Line 18: |
* summary of the remaining tasks * OMC |
* summary of the remaining tasks (klog) * OMC - Working on the vac cable, PD mounts, OMC frame; started the isolation ratio of OFI |
Line 19: | Line 21: |
* High power testing is going in Hongo (Nakano, Tahara) | |
Line 22: | Line 24: |
* Refcav pumping * RF sources (f1-f3) installation * RF distributor installation * Cabling 30m SMA from the IOO rack to PSL table * EOM/RAM * IMMT2 repairing will start |
|
Line 24: | Line 32: |
* from July 4th Uehara-san (high power EOM) * Fujii-kun (an undergrad student from Niigata U) July 4-11 |
* from July 5th Uehara-san (high power EOM) * Fujii-kun (an undergrad student from Niigata U) July 5-11 |
Regular Meeting 0618
Participants
Kokeyama, Uehara, Izumi, Huang, Prof. Wang, Prof. Sato, Prof. Ohkawa, Prof. Suzuki, Sugai, Fujii. Fujikawa
Announcement
Schedule for Phase-2
Chart https://docs.google.com/spreadsheets/d/19xC6L0TJmjMtuSEoGe7Z7SVVK78MD4S52m0Hm0C5IKw/edit
Punchlist https://docs.google.com/spreadsheets/d/1hHhXEqC5DwITUqYFjVgB-ZnAb53V1C4OlaeYNqjblCI/edit#gid=0
Report from the Last 2 weeks
- PMC installation, integration finished
RefCav re-commissioning (with the PMC transmitting beam) was finished from the optics point of view
- IMC angular control loops were closed
- Input pointing PZT mirrors were installed (pointing to the IMC)
- summary of the remaining tasks (klog)
- OMC - Working on the vac cable, PD mounts, OMC frame; started the isolation ratio of OFI
- MZI - The 2nd IOO chassis, AA/AI filters were installed
- High power testing is going in Hongo (Nakano, Tahara)
Plans for the coming 2 weeks
- Refcav pumping
- RF sources (f1-f3) installation
- RF distributor installation
- Cabling 30m SMA from the IOO rack to PSL table
- EOM/RAM
- IMMT2 repairing will start
Visitors
- from July 5th Uehara-san (high power EOM)
- Fujii-kun (an undergrad student from Niigata U) July 5-11
Absence
- Kokeyama will be away from July 5 - 10
Commissioning Calendar
https://teamup.com/kswnmta8p18h6u1uab
Next meeting
- July 17th