Differences between revisions 2 and 4 (spanning 2 versions)
Revision 2 as of 2018-07-02 10:21:00
Size: 1403
Comment:
Revision 4 as of 2018-07-02 10:25:45
Size: 1495
Comment:
Deletions are marked like this. Additions are marked like this.
Line 4: Line 4:
Kokeyama, Uehara, Izumi, Huang Kokeyama, Uehara, Izumi, Huang, Prof. Wang, Prof. Sato, Prof. Ohkawa, Prof. Suzuki, Sugai, Fujii. Fujikawa
Line 18: Line 18:
 * summary of the remaining tasks (klog)  * summary of the remaining tasks (klog 5402)
Line 21: Line 21:
 * High power testing is going in Hongo (Nakano, Tahara)  * High power testing is going in Hongo (Nakano, Tahara, klog 5431)

Regular Meeting 0618

Participants

Kokeyama, Uehara, Izumi, Huang, Prof. Wang, Prof. Sato, Prof. Ohkawa, Prof. Suzuki, Sugai, Fujii. Fujikawa

Announcement

Schedule for Phase-2

Report from the Last 2 weeks

  • PMC installation, integration finished
  • RefCav re-commissioning (with the PMC transmitting beam) was finished from the optics point of view

  • IMC angular control loops were closed
  • Input pointing PZT mirrors were installed (pointing to the IMC)
  • summary of the remaining tasks (klog 5402)
  • OMC - Working on the vac cable, PD mounts, OMC frame; started the isolation ratio of OFI
  • MZI - The 2nd IOO chassis, AA/AI filters were installed
  • High power testing is going in Hongo (Nakano, Tahara, klog 5431)

Plans for the coming 2 weeks

  • Refcav pumping
  • RF sources (f1-f3) installation
  • RF distributor installation
  • Cabling 30m SMA from the IOO rack to PSL table
  • EOM/RAM
  • IMMT2 repairing will start

Visitors

  • from July 5th Uehara-san (high power EOM)
  • Fujii-kun (an undergrad student from Niigata U) July 5-11

Absence

  • Kokeyama will be away from July 5 - 10

Commissioning Calendar

https://teamup.com/kswnmta8p18h6u1uab

Next meeting

  • July 17th