Differences between revisions 4 and 6 (spanning 2 versions)
Revision 4 as of 2019-08-05 17:01:53
Size: 1452
Comment:
Revision 6 as of 2019-08-05 18:35:47
Size: 2023
Comment:
Deletions are marked like this. Additions are marked like this.
Line 29: Line 29:
  * Modification plan: Aso
  * Experiment: Kokeyama
  * Cavity axis calculation: Somiya
  * The wedge of OMC1 is flipped.
  * Somiya-san simulated the TRANS signal during the cavity scan with the speed in the Kasuya-san's measurement, and it indicates the estimated finesse (400) might be a correct number.
  * Modification plan is fixed.
   * Fabrication of the new jig for the alignment
   * Fabrication of the jig for the mirror gluing.
   * OBS3 will be replaced with the curved mirror with ROC of 500 mm. -> It seems to take a long to purchase.
   * The beam does not hit on QPD2. Some modification is needed. (Akutsu-san)
  
Line 37: Line 42:
   * Michimura-san gave several documents about d-demod.
   * The discussion date has not been fixed yet.
 

IOO meeting 2019 0708

Connection

Zoom2: https://zoom.us/j/6676627462

Participants

Ohkawa, Miyazaki, Somiya, Uehara, Guiguo, Kokeyama, Aso

Announcements

  • The deadline of the registration for the F2F is 7th Aug. Make sure you have registered.
  • If you are planning to work in KAGRA especially in the PSL, you need to attend the commissioning meeting at 1 PM on the day before and on that day.

Conferences

  • August F2F meeting, Toyama, 8/22-24
    • Oral : Overview (Nakano, 5 min), OMC (Somiya, 15 min)
    • Poster : Niigata Univ.

Recent Status

PSL

  • Permission at 1 PM commissioning meeting is needed for an entry.

IMC

OMC, OMMT, OSTM

  • OMC commissioning is on going.
    • The wedge of OMC1 is flipped.
    • Somiya-san simulated the TRANS signal during the cavity scan with the speed in the Kasuya-san's measurement, and it indicates the estimated finesse (400) might be a correct number.
    • Modification plan is fixed.
      • Fabrication of the new jig for the alignment
      • Fabrication of the jig for the mirror gluing.
      • OBS3 will be replaced with the curved mirror with ROC of 500 mm. -> It seems to take a long to purchase.

      • The beam does not hit on QPD2. Some modification is needed. (Akutsu-san)
  • OSTM replacement

Niigata

  • Double demodulation
    • First Koyama-kun will discuss with Michimura-san, and then start the experiment in Kamioka.
      • Michimura-san gave several documents about d-demod.
      • The discussion date has not been fixed yet.
  • Scattering measurement
    • Tsugai-kun and Murakami-kun is working to improve the S/N ratio of the measurement, and they will have a poster at F2F meeting.

Visitor

  • Rana from LIGO ~2 weeks in Sep.
  • Jenny from LIGO ~ 1month in Sep.
  • Anamaria from LIGO ?? in Nov.?

Travel

  • Nakano to LLO ~2 weeks in Oct.

Meeting schedule

  • 9/2 (Mon.)
  • 10/7 (Mon.)
  • 11/5 (Tue.)?
  • 12/2 (Mon.)