Line 1: | Line 1: |
=== Task List for OMC and OFI (updated 18/3/11) === | === Task List for Phase-1 OMC and OFI (updated 18/3/12) === |
Line 3: | Line 3: |
||Pillars for output optics||<:>||<:>||Not yet|| ||OFI breadboard||<:>||<:>||Not yet|| ||OFI optical properties||<:>||<:>||Not yet|| ||Transport fixture for OMC||<:>||<:>||On going|| ||PD Mounts||<:>||<:>||Not yet|| ||QPD Mounts||<:>||<:>||Not yet|| ||Control system for OMC ASC||<:>||<:>||Not yet|| ||OMC suspension frame||<:>||<:>||On going|| ||Cablings||<:>||<:>||Not yet|| ||OFI spacer||<:>||<:>||Not yet|| ||OMC installation||<:>||<:>||Not yet|| ||OFI installation||<:>||<:>||Not yet|| |
||OMMT1/2 mirrors||<:>Hirose||<:>||to be delivered in March|| ||OMMT1/2 suspensions||<:>Ohishi||<:>||planned to be manufactured in fall 2018|| ||OSTM bluk||<:>Hirose||<:>||to be delivered to ICRR on April 5|| ||OSTM polish/coating||<:>Hirose||<:>||to be ordered in April|| ||OSTM suspensions||<:>Ohishi||<:>||planned to be manufactured in fall 2018|| ||Pillars for output optics||<:>Somiya||<:>||Al blocks delivered and sent to TT machine shop|| ||In-vac RF PD/QPDs||<:>Michimura||<:>||Not yet|| ||OFI breadboard||<:>Somiya||<:>||designing|| ||OFI TFP mounts||<:>Somiya||<:>||new mounts being designed|| ||OFI input/output baffle||<:>Somiya||<:>||being designed|| ||OFI beam dump||<:>Somiya||<:>||being considered|| ||OFI optical properties||<:>Otabe/Ribes||<:>||TFP extinction ratio measured|| ||OFI spacer||<:>Somiya||<:>||Not yet|| ||OFI installation||<:>||<:>||Planned in Sep 2018 or earlier|| ||OMC transport fixture||<:>Somiya||<:>||Not yet|| ||OMC PD Mounts||<:>Somiya||<:>||Excelitas PD pin location should be checked|| ||OMC QPD Mounts||<:>Somiya||<:>||QPD pin location should be checked|| ||OMC beam dump||<:>||<:>||Delivered to TT|| ||OMC LSC||<:>||<:>||Partially done|| ||OMC ASC||<:>||<:>||Not yet|| ||OMC suspension frame||<:>Somiya||<:>||Tested some examples but not easy|| ||OMC Cablings||<:>Somiya+someone||<:>||Dsub connectors and AWG32 cables ordered; to be test-manufactured at TT|| ||OMC installation||<:>||<:>||Planned in Sep-Oct 2018|| |
Line 16: | Line 27: |
||Cross-check of the OMC calculations||<:>||<:>||Not yet|| ||Make a control system for OMC in Digital system||<:>||<:>||Not yet|| |
||Cross-check of the OMC/OFI calculations||<:>||<:>||Not yet|| ||Digital system for OMC||<:>||<:>||Not yet|| === Task List for Phase-2 OMC and OFI (updated 18/3/12) === ||OFI suspension||<:>||<:>||Not yet|| ||OFI suspension frame||<:>||<:>||Not yet|| ||OMC silica breadboard||<:>||<:>||to be ordered in March|| ||OMC actuator||<:>||<:>||Not yet|| |
Task List for Phase-1 OMC and OFI (updated 18/3/12)
tasks |
person in charge |
due date |
status |
OMMT1/2 mirrors |
Hirose |
to be delivered in March |
|
OMMT1/2 suspensions |
Ohishi |
planned to be manufactured in fall 2018 |
|
OSTM bluk |
Hirose |
to be delivered to ICRR on April 5 |
|
OSTM polish/coating |
Hirose |
to be ordered in April |
|
OSTM suspensions |
Ohishi |
planned to be manufactured in fall 2018 |
|
Pillars for output optics |
Somiya |
Al blocks delivered and sent to TT machine shop |
|
In-vac RF PD/QPDs |
Michimura |
Not yet |
|
OFI breadboard |
Somiya |
designing |
|
OFI TFP mounts |
Somiya |
new mounts being designed |
|
OFI input/output baffle |
Somiya |
being designed |
|
OFI beam dump |
Somiya |
being considered |
|
OFI optical properties |
Otabe/Ribes |
TFP extinction ratio measured |
|
OFI spacer |
Somiya |
Not yet |
|
OFI installation |
Planned in Sep 2018 or earlier |
||
OMC transport fixture |
Somiya |
Not yet |
|
OMC PD Mounts |
Somiya |
Excelitas PD pin location should be checked |
|
OMC QPD Mounts |
Somiya |
QPD pin location should be checked |
|
OMC beam dump |
Delivered to TT |
||
OMC LSC |
Partially done |
||
OMC ASC |
Not yet |
||
OMC suspension frame |
Somiya |
Tested some examples but not easy |
|
OMC Cablings |
Somiya+someone |
Dsub connectors and AWG32 cables ordered; to be test-manufactured at TT |
|
OMC installation |
Planned in Sep-Oct 2018 |
||
Beacon signal simulation |
Not yet |
||
Cross-check of the OMC/OFI calculations |
Not yet |
||
Digital system for OMC |
Not yet |
Task List for Phase-2 OMC and OFI (updated 18/3/12)
OFI suspension |
Not yet |
||
OFI suspension frame |
Not yet |
||
OMC silica breadboard |
to be ordered in March |
||
OMC actuator |
Not yet |