||Pillars for output optics||<:>||<:>||Not yet||
||OFI breadboard||<:>||<:>||Not yet||
||OFI optical properties||<:>||<:>||Not yet||
||Transport fixture for OMC||<:>||<:>||On going||
||PD Mounts||<:>||<:>||Not yet||
||QPD Mounts||<:>||<:>||Not yet||
||Pillars for output optics||<:>Somiya||<:>||Al blocks delivered and sent to TT machine shop||
||OFI breadboard||<:>Somiya||<:>||designing||
||OFI optical properties||<:>Otabe/Ribes||<:>||TFP extinction ratio measured||
||Transport fixture for OMC||<:>||<:>||Not yet||
||PD Mounts||<:>||<:>||Excelitas PD pin location should be checked||
||QPD Mounts||<:>||<:>||QPD pin location should be checked||
Line 10: Line 10:
||OMC suspension frame||<:>||<:>||On going||
||Cablings||<:>||<:>||Not yet||
||OMC suspension frame||<:>||<:>||Tested some examples but not easy||
||Cablings||<:>||<:>||Dsub connectors and AWG32 cables ordered; to be test-manufactured at TT||
Line 13: Line 13:
||OMC installation||<:>||<:>||Not yet||
||OFI installation||<:>||<:>||Not yet||
||OMC installation||<:>||<:>||Planned in Sep-Oct 2018||
||OFI installation||<:>||<:>||Planned in Sep 2018 or earlier||

Task List for OMC and OFI (updated 18/3/11)

tasks

person in charge

due date

status

Pillars for output optics

Somiya

Al blocks delivered and sent to TT machine shop

OFI breadboard

Somiya

designing

OFI optical properties

Otabe/Ribes

TFP extinction ratio measured

Transport fixture for OMC

Not yet

PD Mounts

Excelitas PD pin location should be checked

QPD Mounts

QPD pin location should be checked

Control system for OMC ASC

Not yet

OMC suspension frame

Tested some examples but not easy

Cablings

Dsub connectors and AWG32 cables ordered; to be test-manufactured at TT

OFI spacer

Not yet

OMC installation

Planned in Sep-Oct 2018

OFI installation

Planned in Sep 2018 or earlier

Beacon signal simulation

Not yet

Cross-check of the OMC calculations

Not yet

Digital system for OMC

Not yet