Task List for Phase-1 OMC and OFI (updated 18/3/12)

tasks

person in charge

due date

status

OMMT1/2 mirrors

Hirose

to be delivered in March

OMMT1/2 suspensions

Ohishi

planned to be manufactured in fall 2018

OSTM bluk

Hirose

to be delivered to ICRR on April 5

OSTM polish/coating

Hirose

to be ordered in April

OSTM suspensions

Ohishi

planned to be manufactured in fall 2018

Pillars for output optics

Somiya

Al blocks delivered and sent to TT machine shop

In-vac RF PD/QPDs

Michimura

Not yet

OFI breadboard

Somiya

designing

OFI TFP mounts

Somiya

new mounts being designed

OFI input/output baffle

Somiya

being designed

OFI beam dump

Somiya

being considered

OFI optical properties

Otabe/Ribes

TFP extinction ratio measured

OFI spacer

Somiya

Not yet

OFI installation

Planned in Sep 2018 or earlier

OMC transport fixture

Somiya

Not yet

OMC PD Mounts

Somiya

Excelitas PD pin location should be checked

OMC QPD Mounts

Somiya

QPD pin location should be checked

OMC beam dump

Somiya

Delivered to TT

OMC LSC

Partially done

OMC ASC

Not yet

OMC suspension frame

Somiya

Tested some examples but not easy

OMC Cablings

Somiya+someone

Dsub connectors and AWG32 cables ordered; to be test-manufactured at TT

OMC installation

Planned in Sep-Oct 2018

Beacon signal simulation

Not yet

Cross-check of the OMC/OFI calculations

Not yet

Digital system for OMC

Not yet

Task List for Phase-2 OMC and OFI (updated 18/3/12)

OFI suspension

Not yet

OFI suspension frame

Not yet

OMC silica breadboard

to be ordered in March

OMC actuator

Not yet