Line 1: | Line 1: |
= Installation work 2018/10-11 | = Installation work 2018/10-11 = |
Line 3: | Line 3: |
=== Installation plan | === Installation plan === |
Line 6: | Line 6: |
=== Installation work === [[https://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0091/T1809176/002/sentitems.txt|Items sent from TT to KAGRA]] [[https://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0091/T1809176/003/Book1.pdf|Screws purchased for OMC/OFI]] === Notes === - It turned out that the Table B is to be moved to the SR2 area for ALS (10/11) - Miyoki-san suggested to use an uninterruptible power supply for the omc laser (10/12) - Akutsu-kun suggested to simply remove a blank flange instead of installing a viewport for the laser injection; Saito-san agreed (10/12) - We found that we need two more male pin (accuglass, 100171) to connect the PZT cables to the Dsub cable (10/12) |
Installation work 2018/10-11
Installation plan
Installation work
Notes
- It turned out that the Table B is to be moved to the SR2 area for ALS (10/11) - Miyoki-san suggested to use an uninterruptible power supply for the omc laser (10/12) - Akutsu-kun suggested to simply remove a blank flange instead of installing a viewport for the laser injection; Saito-san agreed (10/12) - We found that we need two more male pin (accuglass, 100171) to connect the PZT cables to the Dsub cable (10/12)