Line 19: Line 19:
[[attachment:180525_output optics saito.xlsx|Coordinates by Saito-san]]
Line 20: Line 22:

 * It turned out that the Table B is to be moved to the SR2 area for ALS (10/11)
Line 30: Line 30:

 * We moved the Optical Table B (POS table) out from the OMC area; it will be moved to the BS area on Nov 8-9 (10/31)

 * PD/QPD in-air cables should be relocated so as to have the female connectors to the feedthrough (11/1)

Installation work 2018/10-11

Installation plan

Installation Document

Installation work

Items sent from TT to KAGRA

Screws purchased for OMC/OFI

Wiring diagram

Drawings of the frame

Drawings of the frame in the OMC chamber

Coordinates by Saito-san

Notes

  • Miyoki-san suggested to use an uninterruptible power supply for the omc laser (10/12)
  • Akutsu-kun suggested to simply remove a blank flange instead of installing a viewport for the laser injection; Saito-san agreed (10/12)
  • One of the feedthrough flanges on the OMC chamber is not tightly connected as there will be one more cable connected to it for a picomotor (10/16)
  • The feedthroughs cannot be directly connected to the KAGRA Dsub cable; there should be a gender changer inbetween (10/17)
  • We moved the Optical Table B (POS table) out from the OMC area; it will be moved to the BS area on Nov 8-9 (10/31)
  • PD/QPD in-air cables should be relocated so as to have the female connectors to the feedthrough (11/1)