Size: 856
Comment:
|
Size: 970
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 13: | Line 13: |
[[https://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0091/T1809176/004/FromChart4.pdf|Screws purchased for OMC/OFI]] |
|
Line 15: | Line 17: |
- It turned out that the Table B is to be moved to the SR2 area for ALS (10/11) - Miyoki-san suggested to use an uninterruptible power supply for the omc laser (10/12) - Akutsu-kun suggested to simply remove a blank flange instead of installing a viewport for the laser injection; Saito-san agreed (10/12) - We found that we need two more male pin (accuglass, 100171) to connect the PZT cables to the Dsub cable (10/12) |
* It turned out that the Table B is to be moved to the SR2 area for ALS (10/11) * Miyoki-san suggested to use an uninterruptible power supply for the omc laser (10/12) * Akutsu-kun suggested to simply remove a blank flange instead of installing a viewport for the laser injection; Saito-san agreed (10/12) * We found that we need two more male pin (accuglass, 100171) to connect the PZT cables to the Dsub cable (10/12) |
Installation work 2018/10-11
Installation plan
Installation work
Notes
- It turned out that the Table B is to be moved to the SR2 area for ALS (10/11)
- Miyoki-san suggested to use an uninterruptible power supply for the omc laser (10/12)
- Akutsu-kun suggested to simply remove a blank flange instead of installing a viewport for the laser injection; Saito-san agreed (10/12)
- We found that we need two more male pin (accuglass, 100171) to connect the PZT cables to the Dsub cable (10/12)