Installation work 2018/10-11

Installation plan

Installation Document

Installation work

Items sent from TT to KAGRA

Screws purchased for OMC/OFI

Notes

- It turned out that the Table B is to be moved to the SR2 area for ALS (10/11)

- Miyoki-san suggested to use an uninterruptible power supply for the omc laser (10/12)

- Akutsu-kun suggested to simply remove a blank flange instead of installing a viewport for the laser injection; Saito-san agreed (10/12)

- We found that we need two more male pin (accuglass, 100171) to connect the PZT cables to the Dsub cable (10/12)