<<TableOfContents(2)>> == October == === 10/2-10/6 === * ISS (Toyama U, Kokeyama, Nakano) * IMC TRANS DCQPD (assemble also IMMT1T DCQPD) === 10/10- 10/14 === || IOO || IFO || || 1. ISS (PSL) || 2. Beam alignment from IMMT2&PR2 to PR3 || || 3. IMMT/PRM breadboard adjustment || || || 4. IMMT1T DCQPD || || 1. member 1. ToyamaU, Kokeyama 1. Kokeyama, Inoue?, Izumi?, Remote Michimura 1. Kokeyama === 10/16 - 10/20 === * Kokeyama will be away from 10/15 - 10/31, 中野君神岡にいてもらうことを了承 || IOO || IFO || || 1. ISS (PSL) || 2. PR3 alignment for EXA|| 1. member 1. Izumi, Inoue, Remote Michimura === 10/23 -10/27 === * Kokeyama will be away || IOO || IFO || || 1. 10/23 消音ダクト工事 (PSL) || 2. EYAに到達するまでのBSアラインメント || 1. 対応川村先生、レーザーつけたままゴーグルで作業してもらう 1. Izumi, Inoue, Remote Michimura === Later in Oct? === * Green beam PSL install - Phase-1後の8月までにはすべてを準備する (ITM1つめ最速8月) == November == * PSL DCQPD install * Tiltsensor? == December == * AC installation in the PSL room |
Schedule 2017 Oct - Dec
Contents
October
10/2-10/6
- ISS (Toyama U, Kokeyama, Nakano)
- IMC TRANS DCQPD (assemble also IMMT1T DCQPD)
10/10- 10/14
IOO |
IFO |
1. ISS (PSL) |
2. Beam alignment from IMMT2&PR2 to PR3 |
3. IMMT/PRM breadboard adjustment |
|
4. IMMT1T DCQPD |
|
- member
- ToyamaU, Kokeyama
- Kokeyama, Inoue?, Izumi?, Remote Michimura
- Kokeyama
10/16 - 10/20
- Kokeyama will be away from 10/15 - 10/31, 中野君神岡にいてもらうことを了承
IOO |
IFO |
1. ISS (PSL) |
2. PR3 alignment for EXA |
- member
- Izumi, Inoue, Remote Michimura
10/23 -10/27
- Kokeyama will be away
IOO |
IFO |
1. 10/23 消音ダクト工事 (PSL) |
2. EYAに到達するまでのBSアラインメント |
- 対応川村先生、レーザーつけたままゴーグルで作業してもらう
- Izumi, Inoue, Remote Michimura
Later in Oct?
- Green beam PSL install - Phase-1後の8月までにはすべてを準備する (ITM1つめ最速8月)
November
- PSL DCQPD install
- Tiltsensor?
December
- AC installation in the PSL room