Differences between revisions 16 and 17
Revision 16 as of 2017-10-03 10:32:03
Size: 1642
Comment:
Revision 17 as of 2017-10-03 10:32:29
Size: 1649
Comment:
Deletions are marked like this. Additions are marked like this.
Line 8: Line 8:
 * ISS (Toyama U, Kokeyama, Nakano)  * --(ISS (Toyama U, Kokeyama, Nakano) )--

Schedule 2017 Oct - Dec

October

10/2-10/6

  • ISS (Toyama U, Kokeyama, Nakano)

  • QPD 組み立て IMC TRANS DCQPD (assemble also IMMT1T DCQPD)
  • IMMT1, IMMT2 ミラーをリリースしてアライメント
  • IMMT1 ピコモーター接続、動作テスト
  • IMMT2 TRANS、Oplev 引き回し
  • Both IMMTs ピコモーターリモート動作テスト
  • STM1, STM2, POM ピコモーター配線がきれていないか確認する
  • 10/3 初期アライメント打ち合わせ

10/10- 10/14

IOO

IFO

1. ISS (PSL)

2. Beam alignment from IMMT2&PR2 to PR3

3. IMMT/PRM breadboard adjustment

4. IMMT1T DCQPD

  1. member
  2. ToyamaU, Kokeyama
  3. Kokeyama, Inoue?, Izumi?, Remote Michimura
  4. Kokeyama

10/16 - 10/20

  • Kokeyama will be away from 10/15 - 10/31, 中野君神岡にいてもらうことを了承

IOO

IFO

1. ISS (PSL)

2. PR3 alignment for EXA

3. 10/18 真空シャッターテスト続き(宗宮)

10/23 -10/27

  • Kokeyama will be away

IOO

IFO

1. 10/23 消音ダクト工事 (PSL)

2. EYAに到達するまでのBSアラインメント

  1. 対応川村先生、レーザーつけたままゴーグルで作業してもらう
  2. Izumi, Inoue, Remote Michimura

Later in Oct?

  • Green beam PSL install - Phase-1後の8月までにはすべてを準備する (ITM1つめ最速8月)

November

  • PSL DCQPD install
  • Tiltsensor?

December

  • AC installation in the PSL room

KAGRA/Subgroups/IOO/scheduleLastHalf (last edited 2018-02-07 09:29:53 by KeikoKokeyama)