Schedule 2017 Oct - Dec
Contents
October
10/2-10/6
ISS (Toyama U, Kokeyama, Nakano)
QPD 組み立て IMC TRANS DCQPD (assemble also IMMT1T DCQPD) => ペデスタル購入/スペーサ製作
- IMMT1, IMMT2 ミラーをリリースしてアライメント
IMMT1 Done http://klog.icrr.u-tokyo.ac.jp/osl/?r=3448
- IMMT2
IMMT1,2 ピコモーター接続、動作テスト Done http://klog.icrr.u-tokyo.ac.jp/osl/?r=3449
- IMMT2 TRANS、Oplev 引き回し
STM1, STM2, POM ピコモーター配線がきれていないか確認する => きれてないっぽいが・・
IMC/refcav normalization button http://klog.icrr.u-tokyo.ac.jp/osl/?r=3454
10/10- 10/14
IOO |
IFO |
1. ISS (PSL) |
2. Beam alignment from IMMT2&PR2 to PR3 |
3. IMMT/PRM breadboard adjustment |
|
4. IMMT1T DCQPD |
|
- member
- ToyamaU, Kokeyama
- Kokeyama, Inoue?, Izumi?, Remote Michimura
- Kokeyama
10/16 - 10/20
- Kokeyama will be away from 10/15 - 10/31, 中野君神岡にいてもらうことを了承
IOO |
IFO |
1. ISS (PSL) |
2. PR3 alignment for EXA |
3. 10/18 真空シャッターテスト続き(宗宮) |
|
10/23 -10/27
- Kokeyama will be away
IOO |
IFO |
1. 10/23 消音ダクト工事 (PSL) |
2. EYAに到達するまでのBSアラインメント |
- 対応川村先生、レーザーつけたままゴーグルで作業してもらう
- Izumi, Inoue, Remote Michimura
Later in Oct?
Green beam PSL install - Phase-1後の8月までにはすべてを準備する (ITM1つめ最速8月)
November
December
12/10
PMC (1st box) was delivered photo
12/14
- Tiltsensors (3) were delivered
12/13
- ISS electronics install
- PSL model and daqd needs to be restarted
- Dsub cables should be tightened on servo
- AC installation in the PSL room