Schedule 2017 Oct - Dec

October

10/2-10/6

  • ISS (Toyama U, Kokeyama, Nakano)
  • IMC TRANS DCQPD (assemble also IMMT1T DCQPD)

10/10- 10/14

IOO

IFO

1. ISS (PSL)

2. Beam alignment from IMMT2&PR2 to PR3

3. IMMT/PRM breadboard adjustment

4. IMMT1T DCQPD

  1. member
  2. ToyamaU, Kokeyama
  3. Kokeyama, Inoue?, Izumi?, Remote Michimura
  4. Kokeyama

10/16 - 10/20

  • Kokeyama will be away from 10/15 - 10/31, 中野君神岡にいてもらうことを了承

IOO

IFO

1. ISS (PSL)

2. PR3 alignment for EXA

  1. member
  2. Izumi, Inoue, Remote Michimura

10/23 -10/27

  • Kokeyama will be away

IOO

IFO

1. 10/23 消音ダクト工事 (PSL)

2. EYAに到達するまでのBSアラインメント

  1. 対応川村先生、レーザーつけたままゴーグルで作業してもらう
  2. Izumi, Inoue, Remote Michimura

Later in Oct?

  • Green beam PSL install - Phase-1後の8月までにはすべてを準備する (ITM1つめ最速8月)

November

  • PSL DCQPD install
  • Tiltsensor?

December

  • AC installation in the PSL room