|| 4月 || Main path || || || || 設計 || || || || 5月 ||FSS install, PMC製作 || || || 治具設計 || 製作 || || || || 6月 || || ||Initial Alignement|| 治具製作、鏡取り出し、接着 ||製作 || || Pickoff || || 7月 ||PMC install || AOM install (after PMC) || || 鏡installation, integration || 製作 || || || || 8月 || || || Lock || Beam profile || 製作 || || || || 9月 || || ISS || WFS || || || || || |
|| 4月 || Main path || || || || Design || || || || 5月 ||FSS install, PMC manufacture || || || Jig design || Manufacture || || || || 6月 || || ||Initial Alignement|| Jig manufacture, glue ||Manufacture || || Pickoff || || 7月 || Beam split || || WFS-II || Mirr installation, integration || Manufacture || || || || 8月 || PMC install || AOM install (after PMC) || Lock || Beam profile, Oplevs, Dampers || Manufacture || || || || 9月 || || ISS || WFS-III || || || || || |
Schedule Overview
Fiscal 2017
|
PSL |
ISS |
IMC |
IMMT |
Tilt |
OMC |
Green |
4月 |
Main path |
|
|
|
Design |
|
|
5月 |
FSS install, PMC manufacture |
|
|
Jig design |
Manufacture |
|
|
6月 |
|
|
Initial Alignement |
Jig manufacture, glue |
Manufacture |
|
Pickoff |
7月 |
Beam split |
|
WFS-II |
Mirr installation, integration |
Manufacture |
|
|
8月 |
PMC install |
AOM install (after PMC) |
Lock |
Beam profile, Oplevs, Dampers |
Manufacture |
|
|
9月 |
|
ISS |
WFS-III |
|
|
|
|
10月 |
|
|
|
|
Installation |
|
Installation |
11月 |
|
|
|
|
|
|
|
12月 |
|
|
|
|
|
|
|
1月 |
|
|
|
|
|
|
|
2月 |
|
|
|
|
|
|
|
3月 |
|
|
|
|
|
|
|