Memo for Commissioning break (Mar. 2020)
Hammering test
'''Task list (Done)'''
- Hammering test of the OMC chamber (Done 22nd Feb.)
- There is excess in the sensitivity between 100 Hz to 400 Hz
- Reported later, the main reason the vibration to the OMC legs for the optical table inside the vacuum
- Hammering test AS table (Done 22nd Feb.)
- Reflection light check (Done 22nd Feb.)
Task list (Partially done)
Task list (todo ; must items)