== Memo for Commissioning break (Mar. 2020) == = Memo for Commissioning break (Mar. 2020) =
Line 3: Line 3:
=== Hammering test === == - Hammering test ==
Line 5: Line 5:
==== Task list (Done) ==== === Task list (Done) ===
Line 15: Line 15:
==== Task list (Partially done) ==== === Task list (Partially done) ===
Line 18: Line 18:
==== Task list (todo ; must items) ==== === Task list (todo ; must items) ===
Line 20: Line 20:
==== Task list (todo ; if possible) ==== === Task list (todo ; if possible) ===

== - PEM injection ==

Memo for Commissioning break (Mar. 2020)

- Hammering test

Task list (Done)

  • Hammering test of the OMC chamber (Done 22nd Feb.)
    • klog13105

    • There is excess in the sensitivity between 100 Hz to 400 Hz
    • Reported later, the main reason the vibration to the OMC legs for the optical table inside the vacuum
  • Hammering test AS table (Done 22nd Feb.)
  • Reflection light check (Done 22nd Feb.)

Task list (Partially done)

Task list (todo ; must items)

Task list (todo ; if possible)

- PEM injection