PEM meeting 2020/07/10(Fri) 16:00-17:00 Zoom2 : https://zoom.us/j/6676627462 No KAGRA wiki page Information * KAGRA interferometer status * Sinet network troble * We couldn’t connect to Kamioka now * It will continue several month in the worst case * Network to Kashiwa server is no problem * Kashiwa network will stop next week 7/15. 7/16 * Due to the unstable of the suspension, we couldn’t lock the PRFPMI now. Sus team is fixing now * Paper status * Status paper (PTEP) submitted to CPC * Acoustic injection(CQG?) ongoing * Post observation * No information from SEO * Still we have several measurements * DRFPMI * Jul. - Aug. * Start from suspension control upgrade * Preparation for O4 * Ondotori maintenance (After allowed the mine work) * Recabling * We will do re-cabling all the PEMs * GND issue * Analysis progress * Washimi (Acoustic injection)