Line 28: Line 28:
   * Pcal finalize->Suspension health check->Acceptance check
   * Commissioning of tower part suspension
   * Suspension health check->Acceptance check
    * Commissioning of tower part suspension
   * PCal/TCam finalize
   * PR3 check
Line 35: Line 37:
   *    * 
Line 70: Line 72:
   * Box install for XY front/end
    * Cabling to Xfront
    * Start project
    * MIC install soon
  * Realtime and medm modification
   * Bug fix
   * Useful medm screen
Line 75: Line 76:
   * Seis for BS/OMC
    * We will perform the vibration test around OMC chamber.
    * We will install seismometer at the week of 27th Sep.
  * Box install for XY front/end
   * Cabling to Xfront
   * Start project
   * MIC install soon
Line 79: Line 81:
   * Voltage monitor   * Seis for BS/OMC
   * Set seismometer around OMC area
   * Prepare the seismometer around BS (Today?)
Line 81: Line 85:
   * Booth MIC setting
    * BS, SR done
  * Voltage monitor
Line 84: Line 87:
   * Table PEM setting (After IMC ASC commissioning)   * Booth MIC setting
   * BS, SR done
Line 86: Line 90:
   * Set calibration factor   * Table PEM setting (After IMC ASC commissioning)

* Set calibration factor
Line 99: Line 105:
    * Middle of October
    * After arriving the geophone for Yend
    * Chamber closing plan
    * 10/5-8
    * Geophone will be set 10/4(Mon)
    * Chamber closing 10/5
Line 123: Line 129:
 * Nishizawa
  * Magnetic field analysis
Line 128: Line 131:
   * Investigation of ICA analysis
  * Progress
Line 135: Line 135:
 * Investigation of ICA analysis
  * Progress

 * Nishizawa
  * Magnetic field analysis
Line 136: Line 142:
  * JPS report [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=13120|JGW-G2113120]]
Line 138: Line 143:
  * Brief report about Xend PCal hammering test
Line 141: Line 147:
  * Analysis of Xend PCal hammering

Weekly PEM meeting

Conference issue

  • 宇宙素粒子若手の会 秋の研究会 URL

    • 11/5-7 @ Kashiwa
    • Registration Deadline : 10/2
  • Other meetings url

  • GWPAW Hannover, Germany, Dec 14th-17th, 2021

If you have some presentation about PEM related, please contact to me.

Business travel

  • Depending on the situation of COVID-19
  • Yokoyama-san 9/28 - 10/01
  • Kobayashi-san /

General issue

  • Interferometer schedule
    • Procedure toward X arm commissioning
      • Suspension health check->Acceptance check

        • Commissioning of tower part suspension
      • PCal/TCam finalize
      • PR3 check
    • IO commissioning
      • IMC ASC
    • IR alignment
    • Mid size baffle installation
    • Y arm commissioning
      • SR3 suspension commissioning
      • Green Y alignment
      • Oplev preparation
  • Schedule
  • PEM schedule
    • Re-installation of PEMs toward O4

Jurnal paper issue

Details are here!

  • PTEP (2) : noise budget(K.Yamamoto, Kokeyama, Washimi) Check list, slack <<Writing>>

    • NB plot has been finalised
    • PWT is checking the draft v0
  • Reverberation time paper (Washimi+) <<Start writing>>

  • ICA for E-run/O3GK (Kume, Yokoyama) <<Analysis ON GOING>>

  • Portable PEMs (Yokozawa+) <<Start writing>>

Preparation for O4

  • PEM cabling
    • XY-end channel assignment JGWDco13125 and cabling

      • Preparation of both XY end PEM channel was done
        • MAG+MIC+ACC, portable around A and C chamber
  • Realtime and medm modification
    • Bug fix
    • Useful medm screen
  • Box install for XY front/end
    • Cabling to Xfront
    • Start project
    • MIC install soon
  • Seis for BS/OMC
    • Set seismometer around OMC area
    • Prepare the seismometer around BS (Today?)
  • Voltage monitor
  • Booth MIC setting
    • BS, SR done
  • Table PEM setting (After IMC ASC commissioning)
  • Set calibration factor
  • New PEM
    • Ondotori
    • Pt 100 by ondotori
    • TEAC710
    • 電界計 (EFM; electric field mill)
    • ACO power supply with low frequency
  • Vibration projection
    • Discussion with CAL team about A chamber
      • 9/21(Tue)
    • Vibration test of OMC chamber
      • 10/5-8
      • Geophone will be set 10/4(Mon)
      • Chamber closing 10/5
  • PEM injection
    • Low-frequency sound injectorklog16829

    • Acoustic injection at X/Y-end
    • Magnetic injection
  • After O4
    • RF monitor
    • Tiltmeter
    • RI detector
    • Newtonian noise
  • Discussion with DET members
    • Daily summary page PEM

Progress report

  • Yuzurihara
    • Interferometer commissioning
    • Pastavi
  • Hoshino
    • Seismic motion analysis
  • Suzuki
    • Water simulation
  • Investigation of ICA analysis
    • Progress
  • Nishizawa
    • Magnetic field analysis
  • Washimi
    • Analysis and simulation for the Schumann resonance
    • Brief report about Xend PCal hammering test
  • Yokozawa
    • Temperature at PSL room
    • Analysis of Xend PCal hammering
  • Seismic motion analysis
    • O3GK
    • Microseismic
    • Long term

Place for memo

KAGRA/Subgroups/PEM/Meeting/211001/Agenda (last edited 2021-10-01 17:04:46 by HirotakaYuzurihara)