Line 7: Line 7:
 * 「素粒子と重力波」研究会 @ OCU
    * https://indico.nitep.osaka-cu.ac.jp/event/92/
    * 2022-02-22
    * Yokoyama & Washimi
Line 25: Line 29:
    * No plan     * Washimi : to OCU (2/22)

Weekly PEM meeting

Meeting and Conference issue

  • 「素粒子と重力波」研究会 @ OCU
    • JPS meeting URL

      • 2022年3月15日(火)~3月19日(土)@ 岡山大学 program

        • 2月中旬に現地開催判断?
        • 横澤(Overview)、鈴木(NN)、粂(non-linear ICA)、小林(O3GK ICA)
        • 鷲見(Noise budget, JGW-G2213473)

    • Other meetings url

If you have some presentation about PEM related, please contact to me.

Business travel

  • Depending on the situation of COVID-19
    • To Kamioka
      • No plan
    • From Kamioka
      • Washimi : to OCU (2/22)

General issue

  • Tonga volcano
    • Ready for uploading to KAGRA HP
  • Procedure toward X arm commissioning
    • IR cavity lock succeeded
  • IO commissioning
    • IMC ASC
  • Mid size baffle installation
    • After IR alignment
  • Y arm commissioning
    • Green Y alignment SR3->ETMY->POS table

    • ETMY alignment done
    • PCal finalize
    • Oplev preparation : ongoing
  • Schedule
  • PEM schedule
    • Re-installation of PEMs toward O4

Jurnal paper issue

Details are here!

  • PTEP (2) : noise budget(K.Yamamoto, Kokeyama, Washimi) JGW-P2113405

    • Collaborator circulation (~1/7)
  • Invited review paper (Washimi+) JGW-P2113549

  • Acoustic reverberation time paper (Washimi+)
    • Washimi will write in the New Year holidays
  • ICA for E-run/O3GK (Kume, Yokoyama)
  • Portable PEMs (Yokozawa+) <<Start writing>>

Preparation for O4

  • PEM installation check
    • Electrical box
      • Cabling plan Xend
    • ACO power supply
  • MN oplev noise investigation
    • Light source??
  • New oplev noise budget
    • EX
    • Main work : Wind, vibration and sound injection FFU on/off
    • Prepare to set the PEMs
      • Accelerometers
      • Seismometer (Move from BS)
      • Magnetometer
      • Microphone
      • PEM injection
  • New PEM
    • PSL room with Cryocon
    • TEAC710
    • 電界計 (EFM; electric field mill)
    • ACO power supply with low frequency
  • Magnetmeters for the Schumann resonance
    • Discussing with technicians (AEL, FCL)
  • PEM injection
    • Low-frequency sound injectorklog16829

    • Acoustic injection at X/Y-end
    • Magnetic injection
  • After O4
    • RF monitor with mokugo
    • Tiltmeter
    • RI detector
    • Newtonian noise
  • Discussion with DET members
    • Daily summary page PEM

Progress report

Place for memo

KAGRA/Subgroups/PEM/Meeting/220204/Agenda (last edited 2022-02-04 10:08:10 by tatsuki.washimi)