Line 203: Line 203:
   * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=14145|JGW-T2214145]]

Weekly PEM meeting

General announcement

  • (LVK inner information) O4 will start from March 2023
  • Important discussion with ET people
    • Magnetic field
    • Meeting of Seismic noise and infrastructure noise (11th July?)
    • If you want to join the discussion, please let Yokozawa know.
  • Visiting to Virgo site
    • By C2C budget
    • Contact to Virgo people
    • End of October -
  • Task list 2022
    • Author list committee ask us to make task list 2022
    • Deadline Jun.4.
    • Task list 2021 pdf

    • If you have question or comments, please let Yokozawa know.

Meeting and Conference issue

  • ET underground infrastructure and noise meeting
    • July 11, 11:00am CEST
  • KAGRA F2F meeting
    • August 1-3
    • Hongo campus
    • Registration url

    • Wiki page url

  • LVK meeting
    • 12-15 September
    • Cardiff Unviersity, UK
  • JPS meeting
    • url

    • 2022/9/6-8 Okayama
      • Washimi : Infrasound
      • Hoshino : Seismic and ocean
  • 日本天文学会
    • 9/13-15
    • 新潟大学
  • ET symposium in Budapest, Hungary
  • GR23 in Beijin, China
  • GWPAW2022 in Melbourne Australia
  • GRASS 2022 in Padova, Italy
  • Other meetings url

If you have some presentation about PEM related, please contact to me.

Business travel

  • Depending on the situation of COVID-19
  • To Kamioka
    • No
  • From Kamioka
    • No

General issue

  • Overall schedule
    • 6/20 - 6/24 Leak of End Y
    • 6/27 - Repair the leak point and start the pumping down
    • 6/20 - 7/1 Suspension commissioning Type-Bp
    • 7/4 - 7/8 Interferometer commissioning
    • 7/11 - 7/22 Suspension commissioning Type-B
    • 7/25 - 7/29 Acceptance check
    • 8/1 - Closing the center area
    • Mid size baffle installation
    • ISS installation
    • High power laser installation
  • Procedure toward X arm commissioning
    • Radiation shield cooling Xend
      • IM temperature is ~90 K
      • Finesse is not changed
  • Mid-size baffle
    • First contact -> Suspension health check -> Mid size baffle install

    • PR2 -> Done

    • SR2 -> Done

    • PRM -> Done

    • BS -> Done

    • PR3 -> Done

    • SR3 -> First contact

    • SRM -> Disassembling -> First contact

  • Y arm commissioning
    • EY leak done : Repair the leak next Monday
    • IY : We will start the duct shield cooling, depending on the pressure level and health check
  • Schedule
  • Type-Bp's suspension health check
  • PEM schedule
    • Re-installation of PEMs toward O4
  • 出張PEM injection (planning form)

    • TAMA300 (June 22)

Jurnal paper issue

Details are here!

  • PTEP (2) : noise budget(K.Yamamoto, Kokeyama, Washimi) JGW-P2113405

  • ICA for E-run/O3GK (Kume, Kobayashi)
    • Sibmitted to CPC
  • Tonga paper (Washimi+)
    • Overleaf, JGW-P2214043

    • CPC circuration has been closed (6/21)
      • Many comments from Yokoyama-san (mainly English corrections)
  • Micro seismic analysis (Hoshino)
  • Acoustic reverberation time paper (Washimi+)
    • Suspend
    • Re-measurement before O4?

Preparation for O4

  • MEDM screen script
    • Just by preparing the channel list, it can reconstruct easily
  • Re-rolating the PEMs
    • IY0 re-location
    • Combination of MAG + barometer
    • Combination of SEIS + barometer
    • Minor change of End PEM channel
  • Barometers and infrasound placement underground
  • Magnetic field underground
    • Discuss with Virgo member next week
    • Fan, ...
  • Seismic and infrastructure noise
  • Magnetmeters for the Schumann resonance
    • ADU (Washimi)
    • Discussing with technicians (AEL, FCL)
  • PEM injection (planning form)

    • Low-frequency sound injectorklog16829

    • Acoustic injection at X/Y-end
    • Magnetic injection (I want to start the preparation soon)
  • After O4
    • RF monitor with mokugo
    • Tiltmeter
    • RI detector
    • Newtonian noise
  • Discussion with DET members
    • Daily summary page PEM

Progress report

Place for memo