Line 72: | Line 72: |
* 6/20 - 6/24 Leak of End Y * 6/27 - Repair the leak point and start the pumping down |
* 6/27 - EY : Repair the leak point and start the pumping down |
Line 77: | Line 76: |
* 7/25 - 7/29 Acceptance check * 8/1 - Closing the center area * Mid size baffle installation |
* 7/25 - 7/29 Acceptance check ~PR2 * 8/1 - 8/5 Closing the center area ~PR2 * 8/8 - 8/19 (Including Obon) Acceptance check ~SRM * 8/22 - 8/26 Closing the center area ~SRM * 8/29 - 9/2 Leak test * Mid size baffle installation partially done (SR3, SRM) * SRM replacement (Week of 7/4) |
Line 82: | Line 85: |
* High power laser installation |
* High power laser installation (Week of 7/4) |
Line 87: | Line 89: |
* IM temperature is ~90 K | * IM temperature is ~80 K |
Line 97: | Line 99: |
* SR3 -> First contact * SRM -> Disassembling -> First contact |
* SR3 -> Done * SRM -> Partially done |
Line 101: | Line 103: |
* EY leak done : Repair the leak next Monday | * EY leak done : Pumping down ongoing |
Line 118: | Line 120: |
* PTEP (2) : noise budget(K.Yamamoto, Kokeyama, Washimi) [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=13405|JGW-P2113405]] * [[https://arxiv.org/abs/2203.07011]] * It has been accepted |
|
Line 127: | Line 126: |
* Arxiv submission | |
Line 128: | Line 128: |
* Many comments from Yokoyama-san (mainly English corrections) | |
Line 141: | Line 140: |
* MEDM screen script * Just by preparing the channel list, it can reconstruct easily * Re-rolating the PEMs * IY0 re-location * Combination of MAG + barometer * Combination of SEIS + barometer * Minor change of End PEM channel |
* PEM installation * To optical table |
Line 182: | Line 175: |
* No special report | |
Line 185: | Line 177: |
* Flow3D meeting | |
Line 203: | Line 196: |
* Rain fall and Water drain * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=14145|JGW-T2214145]] * PEM works at TAMA300 * Seismic and acoustic measurements [[http://www2.nao.ac.jp/~gw-elog/osl/?r=2993]] * hammering test [[http://www2.nao.ac.jp/~gw-elog/osl/?r=2996]] |
* Vibration during drill work * Spectrum of the new PEM |
Line 210: | Line 200: |
* Investigating the MN oplev glitch [[ https://klog.icrr.u-tokyo.ac.jp/osl/?r=21153|klog21153]], [[ https://klog.icrr.u-tokyo.ac.jp/osl/?r=21161|klog21161]] | * Investigating the MN oplev glitch |
Weekly PEM meeting
- 2022/07/01(Fri) 17:00-
- Regular meeting
Zoom2 : https://zoom.us/j/6676627462
General announcement
- KAGRA visiting plan
- Important discussion with ET people
- Magnetic field
- Meeting of Seismic noise and infrastructure noise (11th July?)
- If you want to join the discussion, please let Yokozawa know.
- Visiting to Virgo site
- By C2C budget
- Contact to Virgo people
- End of October -
- Task list 2022
- Author list committee ask us to make task list 2022
- Deadline Jun.4.
Task list 2021 pdf
- If you have question or comments, please let Yokozawa know.
Meeting and Conference issue
- ET underground infrastructure and noise meeting
- July 11, 11:00am CEST
- KAGRA F2F meeting
- LVK meeting
- 12-15 September
- Cardiff Unviersity, UK
- JPS meeting
- 2022/9/6-8 Okayama
- Washimi : Infrasound
- Hoshino : Seismic and ocean
- 日本天文学会
- 9/13-15
- 新潟大学
- ET symposium in Budapest, Hungary
- GR23 in Beijin, China
- GWPAW2022 in Melbourne Australia
- GRASS 2022 in Padova, Italy
Other meetings url
If you have some presentation about PEM related, please contact to me.
Business travel
- Depending on the situation of COVID-19
- To Kamioka
- Fukunaga (7/3-7/9)
- From Kamioka
- F2F related
General issue
- Overall schedule
- 6/27 - EY : Repair the leak point and start the pumping down
- 6/20 - 7/1 Suspension commissioning Type-Bp
- 7/4 - 7/8 Interferometer commissioning
- 7/11 - 7/22 Suspension commissioning Type-B
- 7/25 - 7/29 Acceptance check ~PR2
- 8/1 - 8/5 Closing the center area ~PR2
- 8/8 - 8/19 (Including Obon) Acceptance check ~SRM
- 8/22 - 8/26 Closing the center area ~SRM
- 8/29 - 9/2 Leak test
- Mid size baffle installation partially done (SR3, SRM)
- SRM replacement (Week of 7/4)
- ISS installation
- High power laser installation (Week of 7/4)
- Procedure toward X arm commissioning
- Radiation shield cooling Xend
- IM temperature is ~80 K
- Finesse is not changed
- Radiation shield cooling Xend
- Mid-size baffle
First contact -> Suspension health check -> Mid size baffle install
PR2 -> Done
SR2 -> Done
PRM -> Done
BS -> Done
PR3 -> Done
SR3 -> Done
SRM -> Partially done
- Y arm commissioning
- EY leak done : Pumping down ongoing
- IY : We will start the duct shield cooling, depending on the pressure level and health check
- Schedule
- Type-Bp's suspension health check
- PEM schedule
- Re-installation of PEMs toward O4
出張PEM injection (planning form)
- TAMA300 (June 22)
Jurnal paper issue
- ICA for E-run/O3GK (Kume, Kobayashi)
- Sibmitted to CPC
- Tonga paper (Washimi+)
- Arxiv submission
- CPC circuration has been closed (6/21)
- Micro seismic analysis (Hoshino)
- writing
- Acoustic reverberation time paper (Washimi+)
- Suspend
- Re-measurement before O4?
Preparation for O4
- PEM installation
- To optical table
- Barometers and infrasound placement underground
- Magnetic field underground
- Discuss with Virgo member next week
- Fan, ...
- Seismic and infrastructure noise
- Magnetmeters for the Schumann resonance
- ADU (Washimi)
- Discussing with technicians (AEL, FCL)
PEM injection (planning form)
Low-frequency sound injectorklog16829
- Acoustic injection at X/Y-end
- Magnetic injection (I want to start the preparation soon)
- After O4
- RF monitor with mokugo
- Tiltmeter
- RI detector
- Newtonian noise
- Discussion with DET members
- Daily summary page PEM
Progress report
- Yuzurihara
- Pastavi
- Data Quality Report
- Data quality evaluation
- Suzuki
- Flow3D meeting
- Water simulation
- Hoshino
- Seismic motion analysis
- Kume
- Report of paper progress
- Fukunaga
- Schumann resonance
- Kiyota
- Take over Kobayashi-san's work
- Nishizawa
- Magnetic field analysis
- Washimi
- Vibration during drill work
- Spectrum of the new PEM
- Yokozawa
- Investigating the MN oplev glitch