* End Y : Pumping down ongoing * Suspension health check after pumping down |
* Pumping down ongoing |
Line 85: | Line 84: |
* Suspension health check Type-Bp's * Oplev upgrade : Done * Most work done before acceptance check |
|
Line 90: | Line 86: |
* Investigation of the X-arm fiber noise cancellation * Reason : Tuning of the polarization before injecting the fiber * Xarm : became stable -> Same treatment to Yarm |
|
Line 97: | Line 89: |
* OMC investigation * SRM replacement : Done * Power budget : Done * Beam profile measurement : This weeek |
|
Line 109: | Line 96: |
* Beam dump around IFI * Many ghost beam * beam dumper from reflection beam of the PRM * ALS CARM/DARM * Just started the investigation |
|
Line 142: | Line 136: |
* | * IMMT1 trans ACC * MIC for CRY room and near the IXC air compressor |
Line 145: | Line 140: |
* We will discuss with GIF group next Tuesday | |
Line 182: | Line 178: |
* Updated [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=21494|klog#21494]] | |
Line 206: | Line 201: |
* ET Infrastructure and Active Noise Mitigation divisions meeting (7/11) [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=14176|JGW-G2214176]] * Small hut for infrasound measurement at analysis building [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=21296|klog21296]], [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=21460|klog21460]] * Power line investigation around ITMX [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=21493|klog21493]] * SEM update : GAS page [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=21505|klog21505]] |
* Vibration test of grooving work * Infrasound |
Line 213: | Line 206: |
* Investigating the IMMT oplev glitch |
Weekly PEM meeting
- 2022/07/22(Fri) 17:00-
- Regular meeting
Zoom2 : https://zoom.us/j/6676627462
General announcement
- KAGRA visiting plan
- Welcome to visit KAGRA site
- Please contact to Ohashi-san
- Important discussion with ET people
- Magnetic field from infrastructure
- Meeting of Seismic noise and infrastructure noise (11th July)
- If you want to join the discussion, please let Yokozawa know.
- LVK Newtonian noise
- Presentation at LVK meeting?
- Visiting to Virgo site
- By C2C budget
- Contact to Virgo people
- End of October -
Meeting and Conference issue
- KAGRA F2F meeting
- August 1-3
- Hongo campus
Wiki page url
- LVK meeting
- 12-15 September
- Cardiff Unviersity, UK
- JPS meeting
- 2022/9/6-8 Okayama
- Washimi : Infrasound
- Hoshino : Seismic and ocean
- 日本天文学会
- 9/13-15
- 新潟大学
- ET symposium in Budapest, Hungary
- GR23 in Beijin, China
- GWPAW2022 in Melbourne Australia
- GRASS 2022 in Padova, Italy
Other meetings url
If you have some presentation about PEM related, please contact to me.
Business travel
- Depending on the situation of COVID-19
- To Kamioka
- 7/25, 26 : Araya-san, Takamori-san (ERI, GIF)
- 7/27 : Narita-san and his student (SIT, Lightning)
- From Kamioka
- F2F related (8/1~3, UT Hongo)
General issue
- Overall schedule
- 7/11 - 7/22 Suspension commissioning Type-B
- 7/25 - 7/29 Acceptance check ~PR2
- 8/1 - 8/5 Closing the center area ~PR2
- 8/8 - 8/19 (Including Obon) Acceptance check ~SRM
- 8/22 - 8/26 Closing the center area ~SRM
- 8/29 - 9/2 Leak test
- X arm commissioning
- End X IM 83K
- Investigation of the noise in the new oplev light source
- Investigation of the TMSX beam shape
- Investigation of the ADC noise
- Y arm commissioning
- Pumping down ongoing
- Center area commissioning
- Mid-size baffle SRM : Partially done, need to move to final position
- Study for installation of the new laser
- Set inside the PSL room
- TMSX investigation for ASC
- Position of QPD for alignment sensing and control
- Beam shape investigation
- REFL table investigation
- Check power budget
- Beam dump around IFI
- Many ghost beam
- beam dumper from reflection beam of the PRM
- ALS CARM/DARM
- Just started the investigation
- Schedule
- PEM schedule
- Re-installation of PEMs toward O4
出張PEM injection (planning form)
- TAMA300 (Before or after F2F meeting?)
Jurnal paper issue
- ICA for E-run/O3GK (Kume, Kobayashi)
- Tonga paper (Washimi+)
- English correction : finished
- Submitted to arXiv(v2) and PTEP
- Micro seismic analysis (Hoshino)
- writing
- Acoustic reverberation time paper (Washimi+)
- Suspend
- Re-measurement before O4?
Preparation for O4
- PEM installation
- IMMT1 trans ACC
- MIC for CRY room and near the IXC air compressor
- Barometers and infrasound placement underground
- We will discuss with GIF group next Tuesday
- Magnetic field underground
- Magnetic field from Infrastructure
- Plan : Close the permanent magnetometer close to beam duct
- Seismic and infrastructure noise
- Call for analysis person
- After infrasound microphone installation
- Magnetmeters for the Schumann resonance
- Fukunaga-san's report
- ADU (Washimi)
- Discussing with technicians (AEL, FCL)
- Weather station
- Weather in KAGRA entrance
- New weather station
- Calibration
PEM injection (planning form)
Low-frequency sound injectorklog16829
- Acoustic injection at X/Y-end
- Magnetic injection (I want to start the preparation soon)
- After O4
- RF monitor with mokugo
- Tiltmeter
- RI detector
- Newtonian noise
- Discussion with DET members
- Daily summary page PEM
Progress report
- Yuzurihara
- Pastavi
- Data Quality Report
- Data quality evaluation
- Suzuki
- Water simulation
- Hoshino
- Seismic motion analysis
- Kume
- Report of paper progress
- Fukunaga
- Schumann resonance
- Kiyota
- Take over Kobayashi-san's work
- Nishizawa
- Water newtonian noise
- Magnetic field analysis
- Washimi
- Vibration test of grooving work
- Infrasound
- Yokozawa
- Investigating the MN oplev glitch