Line 48: | Line 48: |
* Plan to have a hammering test toward future blasting | * hammering test toward future blasting (Done) |
Line 64: | Line 64: |
* Week of 3rd June PCAL mirror cleaning * Week of 10th June PCAL alignment |
|
Line 67: | Line 69: |
* Schedule : | * Schedule : Preparation(6/1-10, actual work 6/11-21) |
Line 69: | Line 71: |
* IR/GR alignment recovery : Ongoing * Check the beam position at various mirrors * Cleaning PR2/PR3 |
* IR/GR alignment recovery : Done * Check the beam position at various mirrors (adjust good alignment for O4a ASC) |
Line 80: | Line 81: |
* Submit to PTEP | * Submit to PTEP (2nd submission) |
Line 89: | Line 90: |
* [Important] Strategy for reducing the effect of the acoustic noise * Discuss in Yokozawa part |
|
Line 125: | Line 123: |
* Vibration test around IMC area (Yokozawa?) | |
Line 128: | Line 127: |
* Strategy for reducing the acoustic noise | * Additional Shindo monitor with raspberry pi |
Weekly PEM meeting
- 2024/05/31(Fri) 17:00-
- Regular meeting
Zoom2 : https://zoom.us/j/6676627462
General announcement
- KAGRA Regular Young Researcher Meeting
- Next 19th June (Wed) 17:00-(JST)
- Several Virgo ENV member have some plan to visit KAGRA about 1 month
- One month around Nov.
- They are also thinking about visiting LIGO
- KAGRA would still be commissioning phase
- Plan
- Noise hunting (PEM injection)
- Magnetic injection
- Additional NN measurement
- Other
- O4a noise budget paper
- If you have a plan to write the paper using O4a data and PEM, please let me know.
Meeting and Conference issue
- 2024 Annual Meeting of the Physical Society of Japan
- Start the registration
- GWPAW
- England (2024/05/27-31)
Other meetings url
If you have some presentation about PEM related, please contact to me.
Business travel
- To Kamioka
- Aogaku (6/23-6/27)
- From Kamioka
- Washimi (6/3,4 Naoj)
General issue
- Interferometer recovery
- IMC Recovery : Done (Similar situation around O4a)
- hammering test toward future blasting (Done)
- IFI, IMM, PRM
- Pumping down : Done
- Center area
- Acceptance check(31st May)
- Closing (June)
- Type-A
- IX : Pumping down/ health check ongoing
- EX : Pumping down/ health check ongoing
- IY : Pumping down/ health check ongoing
- EY : Cleaning at EYA
- Week of 20th Water cleaning
- Week of 27th Test of pumping down
- Week of 3rd June PCAL mirror cleaning
- Week of 10th June PCAL alignment
- OMC vibration
- Need to treat something for stacks of OMC chamber
- Schedule : Preparation(6/1-10, actual work 6/11-21)
- IR/GR alignment recovery : Done
- Check the beam position at various mirrors (adjust good alignment for O4a ASC)
出張PEM injection (planning form)
Jurnal paper issue
- Micro seismic analysis (Hoshino)
- Submit to PTEP (2nd submission)
- Acoustic reverberation time paper (Washimi+, Sato?)
- Suspend
- Re-measurement before O4?
Preparation for O4b
- PEM installation
- Waiting the timing of TMSX and TMSY
- Evaluation of newtonian noise
- Anoop and Washimi
- Investigation of the PEM injection
- Magnetic injection
- Voltmeter preparation
- AC power monitor installation
- DC power monitor installation
Progress report
- Yuzurihara
- Pastavi
Data Quality Report slide
- Data quality evaluation
- Sato
- Sound source analysis
- Kume
PR3 line injection klog25670
- Noise subtraction
- Nishizawa
- Water newtonian noise
- Magnetic field analysis
- Washimi
- Vibration test around IMC area (Yokozawa?)
- OMC vibration test
- Yokozawa
- Additional Shindo monitor with raspberry pi