= KAGRA VIS Meeting = 2015/8/5 15:00 - 17:00 First Meeting Room of NAOJ TV conference: 133.40.2.230 SeeVogh: KAGRA VIS == Participants == Shoda, Hirata, Sekiguchi, Fujii, Tatsumi, Mark, Fabian, Akutsu, Ohishi == Discussion == === iKAGRA installation === * Schedule * Currently in the schedule chart, 5 weeks for the in-air assembly (including cabling) + 1 week for in-air tuning is assigned. * Mechanical assembly and cabling will take place alternately. * '''Let me (Aso) know if you have suggestions about the schedule''' * Schedule chart: [[https://www.dropbox.com/s/ukanoq8s8aud6lz/iKAGRA-VIS-Installation-2015.pdf?dl=0]] * Uchiyama-san's slides [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3866]] * Installation Review * We should have a review meeting on the whole installation procedure of Type-Bp suspension early next week * Aso will circulate a Doodle poll * The meeting should be about glueing (Tatsumi), IM assembly (Shoda), mirror hanging (Fabian's document), and everything else (Mark). * Payload test hanging at Mitaka * We may want to do it in the clean room for BF assembly. * Put a bread board on a table there ? Using shims to level the bread board ? * Spare mirror glueing will finish on 8/19. The test assembly can start on 8/24 ? * '''Shoda-san will take charge of this with help from Fabian and students.''' === TAMA experiment === * Current status * Alignment control of the prototype suspension with an optical lever was successful. But not so stable. * RM pitch mode around 5Hz is a problem. '''Could use the RM magnetic damper -> Sekiguchi-kun will try it.''' * Changing the RM wire to thin ones will reduce the resonant frequency of the pitch which makes the control even more difficult. * We probably need to keep using Tungsten wires (higher elestic constant). * We should buy Tungsten wires with several different diameters and try winding with winches to determine the thickness of the wires (thickest possible one). * '''Shoda-san will buy Tungsten wires after consulting with Takahashi-san.''' === Preparation status of the iKAGRA large suspensions === * Cables * '''Review of the cabling plan made by Mark should take place in this week at Mitaka.''' * OSEM * Waiting for parts to arrive: Expected delivery Aug. 23rd. Assebly and calibration will follow. OSEMs will be ready early September. * Satellite box: Talking with AEL group about current limiting resistor. * Got a high power coil driver from AEL === Tyep-Bp temporary damper === * Simulation by Soda-san * http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeBp * Adding OSEMs on the BF to actively damp it seems the best solution * '''Need to check the required force to damp the suspension (Shoda)''' * Fixing the BF to the traverser is another option. It has performance degradation. * Feasibility check of the modifications by Mark * http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3467 * Easiest one seems rigidly connecting the bottom filter to the traverser. * Adding OSEMs are relatively easy. However, moving range of the BF for alignment will be severely limited by the exisitence of the OSEMs. * If we use reflective photo-sensors instead of OSEM, we may be able to increase the adjustment range ? * What to do for the temporary damper * Option 1: Do nothing. We may be able to lock iKAGRA with 5um/sec RMS. Need more considerations. * Option 2: Do the imobilization of the BF for iKAGRA. Change it to a better one for bKAGRA if necessary. * Option 3: Add OSEMs to the BF if we come up with a good idea to keep the adjustment range of the BF. * '''We should decide on the strategy by the next VIS meeting'''