Schedule

KAGRA

Suspension-wise

People-wise

All

ETMX

Takahashi (Type-A leader)

IFO

ITMX

Fabian (Type-B leader)

CAL

ETMY

Sato

ITMY

Hirata

PRs

Ikeda

BS/SRs

Miyo

Input Optics suspensions

Ushiba (CRY)

Output Optics susspensions

Kimura (CRY/VAC)

Transmitter Suspensions (TRs)

Akutsu (AOS)

Old VIS schedule had been used from 2021/03 is in JGW-L2011475

Milestones

<-2>

Installation

In air

In vacuum

In vacuum With IFO

In 100K with IFO

ETMX

#108