== iKAGRA ETM suspension preparation; current status == | == iKAGRA ETM suspension preparation log == |
Line 5: | Line 5: |
* 25th Jan - (2 weeks) Assembling and Hanging with dummy mirror | * 25th Jan - (2 weeks) Assembling and Test Hanging with dummy mirror |
Line 7: | Line 7: |
* 7th Feb- (1 week) check and transportation to the End and installation test | * 7th Feb- (1 week) measurement of transfer function, transportation to the End area and installation test |
Line 10: | Line 10: |
==== Disassembling at Mitaka[Ohishi] ==== finished. (12th-19th) |
==== Disassembling at Mitaka [Ohishi] ==== status: finished. (12th-19th) |
Line 15: | Line 15: |
==== Washing [Hirata-san] ==== most of the parts were washed. |
==== Washing and transportation to Kamioka [Hirata-san] ==== status: finished. |
Line 21: | Line 21: |
Solution: order new screws (not ordered yet) ==== Missing parts ==== * coil bobbin [Takahashi-san] * coil winding [students of Ando-lab] |
Solution: order new screws (by Takahashi-san) ==== New parts ==== * coil bobbin [Takahashi-san] * coil winding [students of Ando-lab] [problem] coil wires from the bobbin to Dsub connector were too short(20cm). Must be 40cm or more. |
Line 26: | Line 27: |
[problem] M3 holes were drilled to phi3.2 holes. | |
Line 27: | Line 29: |
* magnets for dummy mirror (4 ; 2-phi-L-5mm Nd magnets) [Ohishi] | [problem] * magnets for dummy mirror (4 ; 2-phi-L-5mm Nd magnets) [Tomaru, Yamamoto] [] |
Line 29: | Line 33: |
[problem] replaced all Cu screws to stainless. Magnetism problem was indicated. | |
Line 37: | Line 41: |
==== Assembling [Tomaru, Ohishi, Yamamoto]==== | ==== Assembling [Tomaru, Ohishi, Yamamoto] ==== |
Line 44: | Line 48: |
==== Transportation to the End ==== ==== Installation ==== |
iKAGRA ETM suspension preparation log
Schedule
- 12th Jan- (2 weeks) Disassembling and Washing (favorable)
- 25th Jan - (2 weeks) Assembling and Test Hanging with dummy mirror
- 1th Feb- (1 week) coil winding,
- 7th Feb- (1 week) measurement of transfer function, transportation to the End area and installation test
- 15th Feb- installation
Disassembling at Mitaka [Ohishi]
- status: finished. (12th-19th)
- [problem]
- 2 nuts stuck: solved by Hirata-san
- A Cu screw stuck: solved by Hirata-san
Washing and transportation to Kamioka [Hirata-san]
- status: finished.
- [problem]
- ultra sonic washer broken 20th ordered on 22th(Fri) will be arrive at Mitaka on 26th(Tue)
- 8 screws for adjusting the IM holding plate was dirty
- Solution: order new screws (by Takahashi-san)
New parts
- coil bobbin [Takahashi-san]
- coil winding [students of Ando-lab] [problem] coil wires from the bobbin to Dsub connector were too short(20cm). Must be 40cm or more.
- D-sub fixture plates [Takahashi-san] [problem] M3 holes were drilled to phi3.2 holes.
- mirror container [Tatsumi-san] [problem]
- magnets for dummy mirror (4 ; 2-phi-L-5mm Nd magnets) [Tomaru, Yamamoto] []
- some screws in replace with Cu screws [Ohishi] [problem] replaced all Cu screws to stainless. Magnetism problem was indicated.
pico-motors and PZTs
- We have 4 pico-motors except for x-axis (the direction of the light ) y, z, pitch, yaw
coil driver
- We use KAGRA coil driver; we need to cheek its performance.
cables
Assembling [Tomaru, Ohishi, Yamamoto]
- On 21th, suspension frame, security frame, xy stages completed
Hanging
- Hanging jig preparation
Transfer Function Measurement
Transportation to the End