iKAGRA ETM suspension preparation; current status

Schedule

  • 12th Jan- (2 weeks) Disassembling and Washing (favorable)
  • 25th Jan - (2 weeks) Assembling and Hanging with dummy mirror
  • 1th Feb- (1 week) coil winding,
  • 7th Feb- (1 week) check and transportation to the End and installation test
  • 15th Feb- installation

Disassembling at Mitaka [Ohishi]

  • finished. (12th-19th)
  • [problem]
    • 2 nuts stuck: solved by Hirata-san
    • A Cu screw stuck: solved by Hirata-san

Washing [Hirata-san]

  • most of the parts were washed.
  • [problem]
    • ultra sonic washer broken 20th ordered on 22th(Fri) will be arrive at Mitaka on 26th(Tue)
    • 8 screws for adjusting the IM holding plate was dirty
      • Solution: order new screws (not ordered yet)

Missing parts

  • coil bobbin [Takahashi-san]
  • coil winding [students of Ando-lab]
  • D-sub fixture plates [Takahashi-san]
  • mirror container [Tatsumi-san]
  • magnets for dummy mirror (4 ; 2-phi-L-5mm Nd magnets) [Ohishi]
  • some screws in replace with Cu screws [Ohishi]

pico-motors and PZTs

  • We have 4 pico-motors except for x-axis (the direction of the light ) y, z, pitch, yaw

coil driver

  • We use KAGRA coil driver; we need to cheek its performance.

cables

Assembling [Tomaru, Ohishi, Yamamoto]

  • On 21th, suspension frame, security frame, xy stages completed

Hanging

  • Hanging jig preparation

Transfer Function Measurement

Transportation to the End