== iKAGRA ETM suspension preparation; current status == == iKAGRA ETM suspension preparation log ==
Line 4: Line 4:
 * 12th Jan- (2 weeks) Disassembling and Washing (favorable)
 * 25th Jan - (2 weeks) Assembling and Test Hanging with dummy mirror
 * 1th Feb- (1 week) coil winding,   * 7th Feb- (1 week) measurement of transfer function, transportation to the End area and installation test
 * 15th Feb- installation
 * 12th Jan- (2 weeks) Disassembling, Washing, and transportation
 * 25th Jan - (2 weeks) Assembling and Test Hanging with dummy mirror 
 * 7th Feb- (1 week) coil winding, measurement of transfer function, transportation to the End area and installation test
 * 15th Feb- (1 week)installation
Line 10: Line 9:
==== Disassembling at Mitaka [Ohishi] ====
  finished.
(12th-19th)
[problem]
==== Disassembling at ATC Mitaka [Ohishi] (12th-19th Jan.) ====
Line 15: Line 12:
==== Washing [Hirata-san] ====
   most of the parts were washed.
 [problem]
==== Washing and transportation to Kamioka [Hirata-san] ====
Line 21: Line 16:
   Solution: order new screws (not ordered yet)
==== Missing parts ====
 * coil bobbin [Takahashi-san]
 * coil winding [students of Ando-lab]
 * D-sub fixture plates [Takahashi-san]
   Solution: order new screws (by Takahashi-san)
==== New parts ====
 * coil bobbin [Takahashi-san]
  
 * coil winding [students of Ando-lab]
  * coil wires from the bobbin to Dsub connector were too short(20cm). The length of Must be 40cm or more.
  * At the end of coil wires, D-sub pins are swaged. We have run short of pins and waiting for delivery on 29th.
  * Peeling off the coating of wires longer than the length of those pins make the wire broken easily.
 * D-sub fixture plates [Takahashi-san]
  * M3 holes were drilled to phi3.2 holes.
Line 27: Line 27:
 * magnets for dummy mirror (4 ; 2-phi-L-5mm Nd magnets) [Ohishi]   [[attachment:MirrorContainer.pdf|{{attachment:MirrorContainer.pdf||width=600}}]]<<BR>>
* magnets for dummy mirror (4 ; 2-phi-L-5mm Nd magnets) [Tomaru, Yamamoto]
Line 29: Line 31:
    [problem] replaced all Cu screws to stainless. Magnetism problem was indicated.

iKAGRA ETM suspension preparation log

Schedule

  • 12th Jan- (2 weeks) Disassembling, Washing, and transportation
  • 25th Jan - (2 weeks) Assembling and Test Hanging with dummy mirror
  • 7th Feb- (1 week) coil winding, measurement of transfer function, transportation to the End area and installation test
  • 15th Feb- (1 week)installation

Disassembling at ATC Mitaka [Ohishi] (12th-19th Jan.)

  • 2 nuts stuck: solved by Hirata-san
  • A Cu screw stuck: solved by Hirata-san

Washing and transportation to Kamioka [Hirata-san]

  • ultra sonic washer broken 20th ordered on 22th(Fri) will be arrive at Mitaka on 26th(Tue)
  • 8 screws for adjusting the IM holding plate was dirty
    • Solution: order new screws (by Takahashi-san)

New parts

  • coil bobbin [Takahashi-san]
  • coil winding [students of Ando-lab]
    • coil wires from the bobbin to Dsub connector were too short(20cm). The length of Must be 40cm or more.
    • At the end of coil wires, D-sub pins are swaged. We have run short of pins and waiting for delivery on 29th.
    • Peeling off the coating of wires longer than the length of those pins make the wire broken easily.
  • D-sub fixture plates [Takahashi-san]
    • M3 holes were drilled to phi3.2 holes.
  • mirror container [Tatsumi-san]
  • magnets for dummy mirror (4 ; 2-phi-L-5mm Nd magnets) [Tomaru, Yamamoto]
  • some screws in replace with Cu screws [Ohishi] [problem] replaced all Cu screws to stainless. Magnetism problem was indicated.

pico-motors and PZTs

  • We have 4 pico-motors except for x-axis (the direction of the light ) y, z, pitch, yaw

coil driver

  • We use KAGRA coil driver; we need to cheek its performance.

cables

Assembling [Tomaru, Ohishi, Yamamoto]

  • On 21th, suspension frame, security frame, xy stages completed

Hanging

  • Hanging jig preparation

Transfer Function Measurement

Transportation to the End

Installation