Differences between revisions 22 and 23
Revision 22 as of 2016-02-22 10:24:03
Size: 2123
Editor: NaokoOhishi
Comment:
Revision 23 as of 2016-02-23 12:05:25
Size: 2118
Editor: NaokoOhishi
Comment:
Deletions are marked like this. Additions are marked like this.
Line 3: Line 3:
==== original schedule ==== ==== Schedule ====
Line 22: Line 22:
  

iKAGRA ETM suspension preparation log

Schedule

  • 12th Jan- (2 weeks) Disassembling, Washing, and transportation
  • 25th Jan - (2 weeks) Assembling and Test Hanging with dummy mirror
  • 7th Feb- (1 week) coil winding, measurement of transfer function, transportation to the End area and installation test
  • 15th Feb- (1 week)installation

Disassembling at Mitaka [Ohishi]

  • status: finished. (12th-19th)
  • 2 nuts stuck: solved by Hirata-san
  • A Cu screw stuck: solved by Hirata-san

Washing and transportation to Kamioka [Hirata-san]

  • status: finished.
  • ultra sonic washer broken 20th ordered on 22th(Fri) will be arrive at Mitaka on 26th(Tue)
  • 8 screws for adjusting the IM holding plate was dirty
    • Solution: order new screws (by Takahashi-san)

New parts

  • status: finished.
  • coil bobbin [Takahashi-san]
  • coil winding [students of Ando-lab]
    • coil wires from the bobbin to Dsub connector were too short(20cm). The length of Must be 40cm or more.
    • At the end of coil wires, D-sub pins are swaged. We have run short of pins and waiting for delivery on 29th.
    • Peeling off the coating of wires longer than the length of those pins make the wire broken easily.
  • D-sub fixture plates [Takahashi-san]
    • M3 holes were drilled to phi3.2 holes.
  • mirror container [Tatsumi-san]
    • reference
  • magnets for dummy mirror (4 ; 2-phi-L-5mm Nd magnets) [Tomaru, Yamamoto]
  • some screws in replace with Cu screws [Ohishi] [problem] replaced all Cu screws to stainless. Magnetism problem was indicated.

pico-motors and PZTs

  • We have 4 pico-motors except for x-axis (the direction of the light ) y, z, pitch, yaw

coil driver

  • We use KAGRA coil driver; we need to cheek its performance.

cables

Assembling [Tomaru, Ohishi, Yamamoto]

  • On 21th, suspension frame, security frame, xy stages completed

Hanging

  • Hanging jig preparation

Transfer Function Measurement

Transportation to the End

Installation

KAGRA/Subgroups/VIS/Type-C (last edited 2020-04-30 12:05:11 by KousekiMiyo)