Line 5: Line 5:
 * 25th Jan - (2 weeks) Assembling and Test Hanging with dummy mirror  * 25th Jan - (2 weeks) Assembling and Test Hanging with an Al dummy mirror
Line 9: Line 9:
==== Disassembling at Mitaka [Ohishi] ====
  status: finished.
(12th-19th)
  * 2 nuts stuck: solved by Hirata-san
  * A Cu screw stuck: solved by Hirata-san
==== Disassembling at ATC Mitaka [Ohishi] (12th-19th Jan.) ====
  * Two nuts stuck. Hirata-san removed them.
  * A Cu screw stuck. Hirata-san removed it.
Line 14: Line 13:
  status: finished.
  * ultra sonic washer broken 20th
 
ordered on 22th(Fri) will be arrive at Mitaka on 26th(Tue)
  * 8 screws for adjusting the IM holding plate was dirty
   Solution: order new screws (by Takahashi-san)
  * The ultra sonic washer at ATC was broken on 20th Jan.
  A new washer was ordered on 22th(Fri) and arrived at Mitaka on 25th(Mon).
  * Eight screws for adjusting the IM holding plate was dirty.
  Takahashi-san ordered similar screws.
Line 20: Line 18:
  status: finished.
 * coil bobbin [Takahashi-san]
  
 * coil winding [students of Ando-lab]
  * coil wires from the bobbin to Dsub connector were too short(20cm). The length of Must be 40cm or more.
  * At the end of coil wires, D-sub pins are swaged. We have run short of pins and waiting for delivery on 29th.
 * Coil bobbin [Takahashi-san, Tatsumi-san]
  [[http://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0047/T1604741/001/Coil_Preparation_2016.pdf|coil bobbin]]
  * The outer diameter of the coil has been changed from 14.2mm to 14.5mm.
  * Due to this change, the number of winding becomes 39 from 41.
  * Delivered to Kamioka on 4th Feb.
 * Coil winding [Kuwahara-san, and Ushiba-san from U-Tokyo, and Lee-san from Okazaki]
  * We used coil winding machine.
  * Lead wires from the bobbin to Dsub connector were too short (20cm). The length must be 40cm or more.
  * At the end of the lead wires, D-sub pins are swaged. We have run short of pins and waiting for delivery on 29th Feb(Mon).
Line 27: Line 28:
 * D-sub fixture plates [Takahashi-san]
  * M3 holes were drilled to phi3.2 holes.
 * mirror container [Tatsumi-san]
  * reference
 * m
agnets for dummy mirror (4 ; 2-phi-L-5mm Nd magnets) [Tomaru, Yamamoto]
 * D-sub connector plates [Takahashi-san]
 [[attachment:D-sub_connector_plate.pdf|{{attachment:D-sub_connector_plate.pdf||width=600}}]]<<BR>>

  * M3 holes were changed to phi3.1 holes. We used drilling machine at Kamioka surface office.
 *15pin-9pin changer[Ushiba-san, Ohishi]
 * M
irror container [Tatsumi-san]
  [[attachment:MirrorContainer.pdf|{{attachment:MirrorContainer.pdf||width=600}}]]<<BR>>
 
* Magnets for dummy mirror (4 ; 2-phi-L-5mm Nd magnets) [Tomaru, Yamamoto]
Line 33: Line 36:
 * some screws in replace with Cu screws [Ohishi]  * Screws in replace with Cu screws [Ohishi]
Line 35: Line 38:
==== pico-motors and PZTs ==== ==== Pico-motors and PZTs ====
Line 38: Line 41:
==== coil driver ==== ==== Coil driver ====
Line 40: Line 43:
==== cables ==== ==== Cables ====
Line 42: Line 45:
==== Assembling [Tomaru, Ohishi, Yamamoto] ==== ==== Assembling [Tomaru-san, Ohishi, Yamamoto-san] ====
Line 50: Line 53:
==== Transportation to the End ==== ==== Transportation to the End [Prof. Kimura, Sawada-san, Tomaru-san(KEK),]====
 KEK
Line 52: Line 56:
==== Mirrors ====
 Two TAMA PRM mirrors (with about 50% and 90% reflectivities each, resultant contrast becomes 96%) were delivered to Kamioka on 12th Feb.
 
==== Stages ====
 * Condensation
 * Vacuum compatibility?
Line 53: Line 63:
[[attachment:Layout.png|{{attachment:Layout.png||width=600}}]]<<BR>>

iKAGRA ETM suspension preparation log

Schedule

  • 12th Jan- (2 weeks) Disassembling, Washing, and transportation
  • 25th Jan - (2 weeks) Assembling and Test Hanging with an Al dummy mirror
  • 7th Feb- (1 week) coil winding, measurement of transfer function, transportation to the End area and installation test
  • 15th Feb- (1 week)installation

Disassembling at ATC Mitaka [Ohishi] (12th-19th Jan.)

  • Two nuts stuck. Hirata-san removed them.
  • A Cu screw stuck. Hirata-san removed it.

Washing and transportation to Kamioka [Hirata-san]

  • The ultra sonic washer at ATC was broken on 20th Jan. A new washer was ordered on 22th(Fri) and arrived at Mitaka on 25th(Mon).
  • Eight screws for adjusting the IM holding plate was dirty. Takahashi-san ordered similar screws.

New parts

  • Coil bobbin [Takahashi-san, Tatsumi-san]
    • coil bobbin

    • The outer diameter of the coil has been changed from 14.2mm to 14.5mm.
    • Due to this change, the number of winding becomes 39 from 41.
    • Delivered to Kamioka on 4th Feb.
  • Coil winding [Kuwahara-san, and Ushiba-san from U-Tokyo, and Lee-san from Okazaki]
    • We used coil winding machine.
    • Lead wires from the bobbin to Dsub connector were too short (20cm). The length must be 40cm or more.
    • At the end of the lead wires, D-sub pins are swaged. We have run short of pins and waiting for delivery on 29th Feb(Mon).
    • Peeling off the coating of wires longer than the length of those pins make the wire broken easily.
  • D-sub connector plates [Takahashi-san]

    attachment:D-sub_connector_plate.pdf

    • M3 holes were changed to phi3.1 holes. We used drilling machine at Kamioka surface office.
  • 15pin-9pin changer[Ushiba-san, Ohishi]
  • Mirror container [Tatsumi-san]
  • Magnets for dummy mirror (4 ; 2-phi-L-5mm Nd magnets) [Tomaru, Yamamoto]
  • Screws in replace with Cu screws [Ohishi] [problem] replaced all Cu screws to stainless. Magnetism problem was indicated.

Pico-motors and PZTs

  • We have 4 pico-motors except for x-axis (the direction of the light ) y, z, pitch, yaw

Coil driver

  • We use KAGRA coil driver; we need to cheek its performance.

Cables

Assembling [Tomaru-san, Ohishi, Yamamoto-san]

  • On 21th, suspension frame, security frame, xy stages completed

Hanging

  • Hanging jig preparation

Transfer Function Measurement

==== Transportation to the End [Prof. Kimura, Sawada-san, Tomaru-san(KEK),]====

  • KEK

Mirrors

  • Two TAMA PRM mirrors (with about 50% and 90% reflectivities each, resultant contrast becomes 96%) were delivered to Kamioka on 12th Feb.

Stages

  • Condensation
  • Vacuum compatibility?

Installation