Line 4: Line 4:
 12th- (2 weeks) Disassembling and Washing (favorable)
 25th- (2 weeks) Assembling and Hanging
 1th Feb- coil winding, transportation to the End, installation test
 7th Feb- check
 15th installation
 * 12th Jan- (2 weeks) Disassembling and Washing (favorable)
 * 25th Jan - (2 weeks) Assembling and Hanging
 * 1th Feb- coil winding, transportation to the End, installation test
 * 7th Feb- check
 * 15th installation

iKAGRA ETM suspension Preparation; Current status

Schedule

  • 12th Jan- (2 weeks) Disassembling and Washing (favorable)
  • 25th Jan - (2 weeks) Assembling and Hanging
  • 1th Feb- coil winding, transportation to the End, installation test
  • 7th Feb- check
  • 15th installation

Disassembling at Mitaka[Ohishi]

  • finished. (12th-19th)
  • [problem]
    • 2 nuts stuck: solved by Hirata-san
    • A Cu screw stuck: solved by Hirata-san

Washing [Hirata-san]

  • most of the parts were washed.
  • [problem]
    • ultra sonic washer broken 20th ordered on 22th(Fri) will be arrive at Mitaka on 26th(Tue)
    • 8 screws for adjusting the IM holding plate was dirty
      • Solution: order new screws (not ordered yet)

Missing parts

  • coil bobbin [Takahashi-san]
  • coil winding [students of Ando-lab]
  • D-sub fixture plates [Takahashi-san]
  • mirror container [Tatsumi-san]
  • magnets for dummy mirror (4 ; 2-phi-L-5mm Nd magnets) [Ohishi]
  • some screws in replace with Cu screws [Ohishi]

pico-motors and PZTs

coil driver

cables

Assembling

  • On 21th, suspension frame, security frame, xy stages completed [Tomaru]

Hanging

Transfer Function Measurement