== Possible actual schedule of tasks selected from below ==

 * Week of 4/2
  * --(Glue SR3)--
  * --(Build 2xIM)--, 2xIRM
 * Week of 4/9
  * Finish IMs and IRMs
  * Build 1xRM
 * Week of 4/16
  * Start SR3 Hang?
 * Week of 4/23
  * Continue SR3 hang.
 * Week of 4/30
  * (Golden Week)

== Tasks held over from March for lack of time ==
 * Top filter disassembly
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
 * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
 * Do buoyancy calculation (see LIGO-T1100616).
 * Set up SR2 Guardian.
 * Install damping filters for SR2.

== Things we're NOT doing in March OR April because we'd have to bump something else ==
 * Top filter disassembly

== Tasks that we have the necessary items for by the beginning of March ==

[[KAGRA/Subgroups/VIS/TypeB/March2018]]

== Tasks that we have the necessary items for by the beginning of April ==
Line 9: Line 41:
  * First cylinder part arrives ≈4/2; others to follow.
 *
  * First cylinder part arrives ≈4/2 from ATC but needs cleaning by company => ≈4/9
  * Second
to follow about two weeks later (≈4/23).

Stuff for Type B to do in April 2018 while waiting for deliveries

Possible actual schedule of tasks selected from below

  • Week of 4/2
    • Glue SR3

    • Build 2xIM, 2xIRM

  • Week of 4/9
    • Finish IMs and IRMs
    • Build 1xRM
  • Week of 4/16
    • Start SR3 Hang?
  • Week of 4/23
    • Continue SR3 hang.
  • Week of 4/30
    • (Golden Week)

Tasks held over from March for lack of time

  • Top filter disassembly
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Do buoyancy calculation (see LIGO-T1100616).
  • Set up SR2 Guardian.
  • Install damping filters for SR2.

Things we're NOT doing in March OR April because we'd have to bump something else

  • Top filter disassembly

Tasks that we have the necessary items for by the beginning of March

KAGRA/Subgroups/VIS/TypeB/March2018

Tasks that we have the necessary items for by the beginning of April

  • Install LBB damper rings in tanks.
    • First set arrives ≈3/26.
    • ≈2 days work each for 3-4 people.
  • Build SR3 and SRM IMs.
    • Parts for both arrive 3/30.
  • Build SR3 and SRM RMs
    • First cylinder part arrives ≈4/2 from ATC but needs cleaning by company => ≈4/9

    • Second to follow about two weeks later (≈4/23).