== Possible actual schedule of tasks selected from below == * Week of 4/2 * --(Glue SR3)-- * --(Build 2xIM)--, 2xIRM * Week of 4/9 * Finish IMs and IRMs * Build 1xRM * Week of 4/16 * Start SR3 Hang? * Week of 4/23 * Continue SR3 hang. * Week of 4/30 * (Golden Week) == Tasks held over from March for lack of time == * Top filter disassembly * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass. * Do buoyancy calculation (see LIGO-T1100616). * Set up SR2 Guardian. * Install damping filters for SR2. == Things we're NOT doing in March OR April because we'd have to bump something else == * Top filter disassembly == Tasks that we have the necessary items for by the beginning of March == [[KAGRA/Subgroups/VIS/TypeB/March2018]] == Tasks that we have the necessary items for by the beginning of April == |
|
Line 9: | Line 41: |
* First cylinder part arrives ≈4/2; others to follow. * |
* First cylinder part arrives ≈4/2 from ATC but needs cleaning by company => ≈4/9 * Second to follow about two weeks later (≈4/23). |
Stuff for Type B to do in April 2018 while waiting for deliveries
Possible actual schedule of tasks selected from below
- Week of 4/2
Glue SR3
Build 2xIM, 2xIRM
- Week of 4/9
- Finish IMs and IRMs
- Build 1xRM
- Week of 4/16
- Start SR3 Hang?
- Week of 4/23
- Continue SR3 hang.
- Week of 4/30
- (Golden Week)
Tasks held over from March for lack of time
- Top filter disassembly
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Do buoyancy calculation (see LIGO-T1100616).
- Set up SR2 Guardian.
- Install damping filters for SR2.
Things we're NOT doing in March OR April because we'd have to bump something else
- Top filter disassembly
Tasks that we have the necessary items for by the beginning of March
KAGRA/Subgroups/VIS/TypeB/March2018
Tasks that we have the necessary items for by the beginning of April
- Install LBB damper rings in tanks.
- First set arrives ≈3/26.
- ≈2 days work each for 3-4 people.
- Build SR3 and SRM IMs.
- Parts for both arrive 3/30.
- Build SR3 and SRM RMs
First cylinder part arrives ≈4/2 from ATC but needs cleaning by company => ≈4/9
- Second to follow about two weeks later (≈4/23).