Stuff for Type B to do in April 2018 while waiting for deliveries
Possible actual schedule of tasks selected from below
- Week of 4/2
- Glue SR3 (if available - still uncertain)
- Build 2xIM, 2xIRM
- Week of 4/9
- Finish IMs and IRMs
- Build 1xRM
- Week of 4/16
- Start SR3 Hang?
- Week of 4/23
- Week of 4/30
Tasks held over from March for lack of time
- Geophones
- Top filter disassembly
- SF inspection/test/setup
- BF rebuild
Tasks that we have the necessary items for by the beginning of April
- Install LBB damper rings in tanks.
- First set arrives ≈3/26.
- ≈2 days work each for 3-4 people.
- Build SR3 and SRM IMs.
- Parts for both arrive 3/30.
- Build SR3 and SRM RMs
First cylinder part arrives ≈4/2 from ATC but needs cleaning by company => ≈4/9
- Second to follow about two weeks later (≈4/23).